Check that all preparations have been completed correctly prior to
starting commissioning. Commissioning is divided into two phases.
Commissioning preparation is used to monitor the installation
phase and should be performed prior to commissioning.
INFORMATION: Only allow trained service technicians to commis‐
sion the system. Check that the system has been installed cor‐
rectly and that work has been performed in line with the check-lists.
The consequences of failure to use protective
equipment
The operator is responsible for the consequences
of the failure to use protective equipment and dis‐
regard for the warnings in this document.
The use of personal protective equipment is speci‐
fied in the regulations applicable at the installation
place. The consequences of disregarding these
regulations are likewise explained in these local
regulations.
1.
Check the system connectors, fuses and external connec‐
tions on the product and brine tanks.
Check that the hydrogen circuit complies with the regulations
and the room is sufficiently ventilated.
Check that all lines comply with the
‘P&ID’ .
2.
Switch on the main switch.
Check that the voltage is 230 V AC between the phases 400
V AC and between a phase and the neutral conductor and
between a phase and the protective earth.
3.
Main fuse
Note that different main fuses can be fitted
depending on the power supply used, partic‐
ularly in relation to the rated current.
Switch on the main fuse in the control cabinet.
4.
Switch on the 24 V AC/24 V DC power supply.
Measure whether there is 24 V AC at the 24 V AC terminal
and 24 V DC at the 24 V DC terminal
5.
Open the water inlet valve of your system and check that the
water lines are leak-tight.
6.
Check that the water supply has adequate pressure (1.5 bar
± 0.5 bar) and use the pressure regulating valve to adjust if
necessary.
7.
Use the test kit to measure the hardness of the supply water.
The scope of delivery of the system includes a test kit for
measuring the water hardness. Measure the hardness of the
supply water upstream of the softener. Follow the instructions
for the water hardness test in the test kit manual.
ð
Use the measured value to further configure the system.
Commissioning
41
Summary of Contents for Chlorinsitu-III
Page 18: ...A1706 15 4 13 3 3 16 12 17 Fig 8 Components of the system side B Components of the system 18 ...
Page 117: ...117 ...
Page 118: ...118 ...
Page 119: ...119 ...