3 weeks
Concrete base and
cable duct
- Based on the drawings at the end of this manual,
make the concrete plinth in the area of installation of
the radio telescope.
- Prepare an underground duct from the base on which
the radio telescope is going to be installed to the
control room. The duct must contain the coaxial cables
connecting the two LNAs to the receiver and the power
supply and control cable of the mount. The duct must
have a minimum diameter of 15 cm (6 inc). Since the 2
LNA power cables have a large diameter (to avoid
signal leakage), they are rigid so the channel must not
have narrow curves that prevent cable passage.
- Prepare 2 groundings, that has to be dimensioned
based on the legislation of the country of installation.
One grounding will be closed to the pier base and one
grounding will be in the control room (to connect the
surge protectors of the receiver).
2 weeks
Installation of cable
connections
- Have LNA power cables and electrical wiring and
power supply cables are to be installed in the in-ground
conduit by qualified personnel (electrician). The cables
are shipped from PrimaLuceLab to the customer in
advance on the delivery of the telescope.
1 week
Safety
- Before the delivery of the SPIDER 300A radio
telescope, ensure that all safety conditions are
complied according to the regulations in force in the
Country of use.
At installation and start-
up
Installation
- Have the connection of the SPIDER 300A
radiotelescope made by specialized professionals.
Period before delivery Planning Criteria
proceedings
pag. 10