Installation guide 

 Flash Mix 

 PSA-240HD 

 

 

Edition: 2019-01-09 

Flash Mix -  PSA-240HD 

Installation guide 

 
 

This guide provides information regarding the installation, operation and maintenance of the PSA-240HD 
Flash Mix  from Premier Tech Aqua. For additional information, contact our customer service at 1 800 
632-6356 

 
 

Table of content 

1

 

Installation steps........................................................................................................................... 1

 

2

 

Pumps performance curves .......................................................................................................... 3

 

3

 

Pumping station start-up and adjustment ...................................................................................... 3

 

4

 

Maintenance ................................................................................................................................. 3 

 
 
 

1

 

Installation steps 

1.1

 

Step 1 

 Excavating, bedding preparation and placing of the pumping station 

 

Excavate  the  required  area  by  respecting  the  minimum 
distances shown on the adjacent illustration. 

 

Level  and  compact  the  bedding  material  (H2)  which 
consists of Ø 0-20 mm (0-¾") gravel or sand.  

 

Place  the  pumping  station  on  a  level  and  stable  layer  of 
fine gravel.  

 

The pumping station must be accessible at all times and 
must be 50 mm (2") above the surface of the landscaped 
lot. 

 

A maximum of two (2) PSR-140 risers is allowed. 

 
 

1.2

 

Step 2 

 Pipe connections 

 

Connect the previous tank to the pumping station using a pipe that complies with the regulations. The 
pipe must have a minimum downward slope of 2% towards the pumping station. 

 

Connect the 4” (100 mm) SDR

-

35 exit to the following tank using 4” SDR

-35 pipe. The pipe must have 

a minimum downward slope of 2% towards the pumping station. 

 

Connect the 2” (50 mm) PVC pipe exiting the pump to the phosphorus r

emoval equipment with either 

a 2” PVC SCH80 pipe or a 2” flexible pipe. 

The pipe must withstand at least  700 kPa (100 PSI) of 

pressure and is suitable for underground applications. 

 

Connect the 2” (50 mm) PVC pipe coming from the phosphorus removal 

equipment with e

ither a 2” 

PVC  SCH80  pipe  or  a  2”  flexible  pipe

 

to  the  2”  inlet  pipe  of  the  pumping  station

.  The  pipe  must 

withstand at least 700 kPa (100 PSI) of pressure and is suitable for underground applications. 

 

A vent must be installed on the pumping station.  

 

The pipes must be installed in a way that they drain by gravity. 

 

Precautionary measures against freezing must be taken to protect the pipe connecting the pumping 
station to the treatment system.

 

 