8
PMT EVO 2.0 S
1 Ballast stone
Place 1 ballast stone in the middle of the-
main profile, push it to the base and secure
it using the end clamp.
2 Ballast stones
Place 2 ballast stones in the middle
of the main profile and use the
middle clamp to secure them.
Ballast stones
on the double cross struts: Mount cross
- and ballast struts as described in Step
3 on both tower sides. Place the stones
evenly distributed on the the braces.
4
Position ballast stone
H
3 – 4 Ballast stones
Secure ballast stones 1+2 as described using
middle clamps. Put on ballast stones 3+4 and
push them towards the tower.
H
Maximal
135 kg
per ballast bar arrangement
Always refer to the relevant project
report for the number, positions and
weights of the ballast stones required.
F