1
Construct base as per layout drawing P/QU03/01 ensuring the correct levels for safety
surfacing.
2
Excavate 400mm x 400mm holes for Posts as in drawing P/QU03/02 to a depth of 500mm
(800mm for loose fill)
from finished safety surfacing height. (All Posts have finished ground
level marks)
3
Position the Posts as per drawing P/QU03/02.
All posts are numbered.
(Tap holes with a 10mm tap and make sure bolts are only hand tight at this stage)
4
Fit the Posts in to the excavated holes and connect together using the various components as in
drawing P/QU03/04 and the attached visual.
5
Excavate 400mm x 400mm holes for events as in drawing P/QU03/03 to a depth of 500mm
(800mm for loose fill)
from finished safety surfacing height.
6
Connect the events as per drawing P/QU03/04 using M10 x 30 resistorx & nylon washers.
7
Connect all ropes using the 8mm quick links & vandal pins
9 Once all equipment is fitted check levels again, ensure minimum distances illustrated in
P/QU03/01, tighten all bolts and concrete in to the ground.