Transfer the required project to the USB memory and activate it on the base unit via the
Project Manager on the PNOZmulti Configurator, as described in the online help for the
PNOZmulti Configurator.
}
As the project is loaded, the base unit must be stopped and then restarted.
}
Once the project has been loaded successfully and the device has been restarted, the
status of the supply voltage is shown on the display. The "RUN" LED is lit.
6.6
Activate project via the display on the base unit
A project that is stored on the USB memory can be activated in the base unit via settings on
the display.
Procedure:
}
Make sure that the USB memory containing the current project is plugged into the base
unit PNOZ m B1.
}
Switch on the supply voltage.
}
Stop the device via the multifunction switch on the display via the menu setting
System
mode
->
Stop system
(for details of how to navigate the display see the section entitled
)
}
In the
Project
menu, navigate to the folder containing the required project and select the
project file with the extension
.mpnoz2
.
}
Load the project by pressing the multifunction switch and restart via the menu setting
System mode
->
Restart system
.
6.7
Display settings
Various settings can be made and information displayed via the menu on the device's dis-
play.
6.7.1
Operate menu
The menu settings are made on the device's display via a multifunction switch. You can
switch between the menu levels by pressing or turning the multifunction switch.
Press multifunction switch
}
Confirm selection/setting
}
Switch to sub-menu
}
Exit menu:
\..