GENERAL WARNINGS 

 
The equipment described in this manual is a device subject to pressure installed in systems under pressure. 
The involved equipment is usually embedded in systems conveying flammable gases (e.g. natural gas). 
 

WARNINGS FOR THE OPERATORS 
 

Before performing the installation, commissioning or maintenance, the operators must: 
 

 

go through the safety provisions applicable to the installation where they have to operate; 

 

obtain the necessary authorizations to operate, when required; 

 

be equipped with the necessary personal protective equipment (helmet, goggles, etc.) 

 

make sure that the area in which they have to operate is equipped with the required collective protections as well as 
with the necessary safety signs. 

 

PACKAGING / TRANSPORT / STORAGE 

 

The  packaging  materials  used  for  transporting  the  equipment  and  the  related  spare  parts  have  been  designed  and 
manufactured  to  avoid  damages  during  normal  transport,  storage,  and  related  handling.  Therefore,  the  equipment  and  spare 
parts must be kept in their respective original packages till their installation in the final destination site. When the packages are 
opened,  it  is  necessary  to  verify  the  integrity  of  the  materials  therein  contained.  In  case  of  damages,  report  the  detected 
damages to the suppliers preserving the original package to allow the performance of necessary inspections. 
The storage of the equipment, even after its use, must occur in suitable places, free of moisture and away from sources of light 
and heat, within the limits stated on the rating plate 
 

HANDLING 

 
The  handling  of  the  equipment  and  its  components  must  be  performed  after  having  established  that  the  lifting  means  are 
suitable for the loads to be lifted (lifting capacity and functionality) in order to avoid bumps, impacts and local stresses. 
When necessary, the handling of the equipment must be performed using the lifting points foreseen on the equipment itself. The 
use of motorized means is reserved to authorized personnel only. 
 

INSTALLATION 

 

The installation of the pressure regulator must occur in compliance with the provisions (laws or regulations) in force in the place 
of installation. 
In  detail,  natural  gas  plants  must  show  features  complying  with  the  law  provisions  or  regulations  in  force  in  the  place  of 
installation or at least complying with the standards EN 12186 or EN 12279. The installation in compliance with such standards 
minimizes the risk of fire and the formation of potentially hazardous atmospheres. 
The  equipment  is  not  provided  with  internal  pressure  limitation  devices;  therefore,  it  must  be  installed  making  sure  that  the 
operating pressure of the installation in which it is installed does not exceed the value of the allowable maximum pressure (

PS

).  

The user shall therefore, when he/she deems it necessary,   
provide for the installation on the assembly of suitable pressure limitation systems; Moreover, the user shall equip the plant with 
suitable  relief  or  drain  systems  in  order  to  be  able  to  discharge  the  pressure  and  the  fluid  contained  in  the  plant  before 
proceeding with any inspection and maintenance activity. 
Should the installation of the equipment require the installation on site of compression fittings, these latter have to be installed 
following the instructions provided by the manufacturer of the fittings. The selection of the fittings must be compatible with the 
use specified for the equipment and with the plant specifications, when foreseen. 

 

COMMISSIONING 
 

The commissioning must be carried out by 

suitably trained personnel

During the commissioning, the personnel not strictly necessary must be kept away and the limited access area must be properly 
marked (signs, barriers, etc.). 
Verify that the equipment calibrations are the ones required. If necessary, restore the required values for the same as provided 
for later on in this manual. 
During the commissioning, the risks determined by any discharges to the atmosphere of flammable or noxious gases must be 
assessed. 
For installation on natural gas distribution networks, it is necessary to consider the risk of formation of a (gas/air) explosive mix 
within the piping. 

 

COMPLIANCE WITH DIRECTIVE 97/23/EC (PED) 

 

The regulator 

Dival 500

 is classified as pressure accessory pursuant to Directive 97/23/EC (PED). 

The  regulator 

Dival  500

  with  embedded  slam-shut  device  and  pressure  switch  tripping  in  case  of  maximum  pressure  is 

classified as safety accessory pursuant to the PED Directive and, therefore, it can be used as both a pressure accessory and a 
safety accessory, always pursuant to the PED Directive. 
The  configuration  with  active  regulator  and  monitor  regulator  in  line  is  defined  as  a  safety  accessory  according  to  the  PED 
Directive. In this case, the user is responsible for verifying that the allowable maximum pressure (

PS

) of the pressure equipment 

to be protected is compatible with the calibration of the monitor regulator and its lockup pressure class (

SG

). 

 

 

 

Summary of Contents for DIVAL 500

Page 1: ...EN TECHINICAL MANUAL Pressure Regulators DIVAL500...

Page 2: ...2 MT 235 EN ed 2015 Rev A EN DIVAL Basic version INLET PRESSURE OUTLET PRESSURE DIVAL 500...

Page 3: ...tallation in compliance with such standards minimizes the risk of fire and the formation of potentially hazardous atmospheres The equipment is not provided with internal pressure limitation devices th...

Page 4: ...s transmitted by the lever system 305 to the stem 201 and therefore to the obturator 211 The obturator is provided with a vulcanized rubber gasket in order to assure a perfect tightness when the reque...

Page 5: ...5 MT 235 EN ed 2015 Rev A Figure 1 DIVAL 500 Figure 2 Relief version NO Figure 3 Relief version YES...

Page 6: ...143BI WHITE 34 97 4 5 300 599 64470144VI PURPLE 34 100 5 600 999 64470145AR ORANGE 34 100 5 5 1000 1799 64470151BL BLUE 34 5 100 6 5 1800 2500 De external d wire Lo Length 1 4 RELIEF VALVE CALIBRATION...

Page 7: ...accessible for performing the following maintenance operations see overall dimensions in table 2 1 the inlet and outlet pipings are on the same level and are able to support the regulator weight see t...

Page 8: ...Rp 1 4 DIVAL500 LA 25x25 1 x1 110 255 182 185 5 161 173 Rp 1 4 Rp 1 4 DIVAL500 25x40 1 x1 1 2 130 257 55 185 5 173 Rp 1 4 DIVAL500 LA 25x40 1 x1 1 2 130 257 182 185 5 161 173 Rp 1 4 Rp 1 4 Table 2 2 W...

Page 9: ...ges of sensors membranes shall be conveyed in compliance with the EN 12186 or EN 12279 standards In order to prevent impurities and condensation from building up in the pressure sensing tubes it is ad...

Page 10: ...g its alignment even after the installation of the regulator 3 1 EMBEDDED SLAM SHUT VALVE LA It is a device fig 9 that immediately blocks the gas flow if due to any failures the outlet pressure reache...

Page 11: ...e of the spring 547 This causes the movement of the shaft 535 which by means of the cam moves the touch probe 509 thus releasing the lever mechanism In this way the stem 517 is freed and the obturator...

Page 12: ...GREY 34 42 2 8 140 179 64470116GI YELLOW 34 40 3 2 180 279 64470051BI WHITE 34 50 3 2 280 450 Tripping due to minimum pressure 64470024BI WHITE 15 45 1 3 10 59 64470038GI YELLOW 15 40 2 60 240 De ext...

Page 13: ...ame allows the outlet pressure to reach the calibration value set for the monitor regulator For this emergency device PIETRO FIORENTINI has a solution for installations with an line monitor regulator...

Page 14: ...subsequent discharge of a given quantity of gas As soon as the pressure falls below the calibration value the obturator returns to the closed position The control and adjustment of the relief valve t...

Page 15: ...tions PS maximum allowable pressure that can be born under safety conditions by the device body structure Wds calibration range of the pressure regulator pilot pre reduction unit that can be obtained...

Page 16: ...ons consisting of two lines it is recommended to commission one line at a time starting from the one with the lower calibration value i e the so called spare backup or standby line Before commissionin...

Page 17: ...the adjustment ring nut 549 rotate it counter clockwise to decrease the tripping value trip in case of pressure increase and decrease slowly increase the auxiliary pressure and record the tripping va...

Page 18: ...iary pressure and verify the tripping value If necessary increase the tripping value by rotating clockwise the adjustment ring nut 549 rotate it counterclockwise to decrease the tripping value For the...

Page 19: ...losed position Open the inlet on off valve V1 Very slowly open the slam shut valve by pulling the proper bushing Partially open the relief valve 6 on the outlet piping Using the pressure gauge 5 check...

Page 20: ...means of the suitable bushing 5 Keep the knob 1 pressed and For the safety devices tripping in case of maximum pressure slowly increase the auxiliary pressure and verify the tripping value If necessar...

Page 21: ...ge 4 and 5 check that the outlet pressure shows the calibration value preset for the monitor regulator 1 Should this not be the case adjust the calibration by acting on the proper internal ring nut tu...

Page 22: ...ment 6 2 ANOMALIES OF THE SLAM SHUT DEVICE LA Table 6 2 describes the possible anomalies that the slam shut device may show INCONVENIENCE POSSIBLE CAUSES INTERVENTION The blocking obturator does not c...

Page 23: ...ed To have a set of tools as shown in table 7 5 For proper maintenance the recommended spare parts are unequivocally identified by tags indicating The SS layout drawing number of the equipment in whic...

Page 24: ...ty status 2 Make sure that the pressure upstream and downstream of the same is zero DISASSEMBLING AND RE ASSEMBLING 7 3 REGULATOR DIVAL 500 3 Disconnect the fittings between the regulator and the down...

Page 25: ...ction disc the membrane and the membrane support 10 By raising and lowering them check the proper functioning of the internal lever mechanisms CAUTION INTERNAL RELIEF ACTIVE theO ringmust beinthelower...

Page 26: ...for disassembly in reverse order Before reassembling the tightness elements O rings membranes etc it is necessary to check their integrity and if necessary replace them Moreover it is recommended to...

Page 27: ...ct the fittings between the slam shut valve and the downstream pressure sensing line 3 Remove the screws that secure the slam shut device to the body 4 Remove the slam shut device 5 Unscrew the plug a...

Page 28: ...9 Extract the shaft assembly from the top 10 Unscrew the nut and remove the obturator To re assemble the slam shut valve follow the procedure described for disassembly in reverse order Before reassemb...

Page 29: ...ting very slowly pull the bushing of the slam shut valve until opening only the internal bypass Then when pressure has equalized pull until the coupling is latched position 3 Check the tightness of th...

Page 30: ...Via Enrico Fermi 8 10 36057 Arcugnano VI Tel 39 0444 968511 Fax 39 0444 960468 www fiorentini com R code generated on http qrcode littleidiot be...

Reviews: