2  | 

P a g e  

 

 

5.0

 

Battery Settings and Communication Cable Installation 

CAUTION: Before connecting the battery racks to the Any-Grid(s), please follow the installation instructions in 
this chapter step by step. The battery, AC input source, AC output loads and PV input must remain 
disconnected until instructed otherwise. 

The battery settings in this chapter are recommendations only. They are intended to keep the batteries within their 
operational limits (maximum voltage, maximum current, etc). These settings can be adjusted to optimize the 
performance of your particular system, but must be kept within the limits of the battery specifications. 

1.

 

Purchase the PSW-H-BAT-CABLE-PYLON-2 or PSW-H-BAT-CABLE-PYLON from a Phocos dealer. This cable is 
designed specifically for connecting the Any-Grid PSW-H to Pylontech battery racks. 

2.

 

Ensure the battery racks are turned off. 

3.

 

 

 

Dip Switches location 

 

Locate the four Dip switches as shown above at position

 ➊

 (position may vary on different battery rack 

models). Each switch can be set ON in the top position or OFF in the bottom position. Set the Dip switches as 
follows, depending on the number of battery clusters / groups: 

Dip 1 

Dip 2 

Dip 3 

Dip 4 

Group address 

ON 
 
RS-485 baud 
rate = 9600 

OFF 

OFF 

OFF 

Single group only. The master battery rack must have 
this setting. Slave battery racks should have all Dip 
switches set to OFF. 

ON 

OFF 

OFF 

Two-group configuration. The master battery rack in 
the first group must have this setting. Slave battery 
racks should have all Dip switches set to OFF. 

OFF 

ON 

OFF 

Two-group configuration. The master battery rack in 
the second group must have this setting. Slave 
battery racks should have all Dip switches set to OFF. 

 

4.

 

Ensure the battery racks are still turned off. Connect the Any-Grid(s) to the battery power (positive and 
negative) terminals with the correct polarity. 

5.

 

If you are using the PSW-H-BAT-CABLE-PYLON-2 cable, it is marked with a “PYLON” label on one of the two 
sides: 

 

Connect this side to the master battery rack’s “RS485” port and the other side into the Any-Grid display 
panel’s “BMS” port 

If instead you are using the PSW-H-BAT-CABLE-PYLON, it is not labelled. For this cable it does not matter 
which orientation you choose, as it functions in both orientations: 
 

Summary of Contents for Any-Grid PSW-H-5kW-230/48V

Page 1: ...Any Grid use with Lithium battery models Pylontech US2000 US3000 Phantom S Force L1 and Force L2 Applicable for Any Grid PSW H 5kW 230 48V Recommended battery settings guide ...

Page 2: ...unication cable PSW H BAT CABLE PYLON 2 or alternatively PSW H BAT CABLE PYLON This cable can be purchased separately from your Phocos dealer WARNING Do not use the inverter cable included with your Pylontech batteries Pylontech battery rack s 3 0 System Overview 4 0 Battery Sizing To maintain the full battery warranty each battery rack should be sized not to exceed 25 Adc 37 Adc for the US3000 Fo...

Page 3: ...an be set ON in the top position or OFF in the bottom position Set the Dip switches as follows depending on the number of battery clusters groups Dip 1 Dip 2 Dip 3 Dip 4 Group address ON RS 485 baud rate 9600 OFF OFF OFF Single group only The master battery rack must have this setting Slave battery racks should have all Dip switches set to OFF ON OFF OFF Two group configuration The master battery ...

Page 4: ...e for a system with 4 Any Grids in parallel 6 Ensure the battery racks are wired as outlined in the Pylontech battery manual Turn on each of the battery racks with the power button and ensure the LED near the power button is green for all battery racks 7 To supply the Any Grid s with power press the red START SW on the master battery rack for more than 3 seconds 8 Ensure the ON OFF load power butt...

Page 5: ...12 48 Vdc or higher Voltage set point to switch from Grid mode to Off Grid mode when selecting SBU priority or Solar PV first in settings menu 01 Menu 13 52 Vdc or lower Boost battery charging voltage Menu 26 53 0 Vdc Floating battery charging voltage Menu 27 52 0 Vdc Low voltage disconnect Menu 29 47 0 Vdc Boost battery charging duration Menu 32 60 min Battery equalization Menu 33 Disabled Maximu...

Page 6: ...The number of battery racks and battery groups are shown in the information screen view before the Main unit firmware version U1 as shown below Information Screen View Example Battery rack and battery group quantity Battery parallel rack quantity 8 battery group quantity 2 If errors or warnings are shown consult the Any Grid manual for details Warning codes 60 61 69 and 70 are specific to Lithium ...

Page 7: ...of this document is subject to change without notice Copyright 2020 Phocos AG all rights reserved Version 20200309 Phocos AG Magirus Deutz Str 12 89077 Ulm Germany Phone 49 731 9380688 0 Fax 49 731 9380688 50 www phocos com info phocos com ...