3.1 UNPACKING AND INSPECTION
The following checks are recommended after receipt of the equipment from shipping
agent:
1.
Check for any external damage that could have occurred in transit. If damage is
found, report to the shipping agent and to the supplier immediately.
2.
Check that all items on the packing slip are present. If any are missing, report to
the supplier immediately.
3.
The amplifiers all have been programmed at the factory with the following
settings.
DC Continuity: - J1 and J2 both connected for through power.
Alarm options: - Bias and RF engaged for both bands.
Alarm Code:
- Consecutive numbers assigned.
(Check for duplication if two lots used).
Attenuation: - -Set to zero attenuation in both bands if autoset board not
installed.
It is suggested that known changes required to these settings be made on the
bench before the units are installed at the site. Consult section 4.0 for more