Foundation frame RF01 0-01 

 

 

5.3  Installation 

  Prepare foundation for the frame, sized 2000x1700 mm 200-250 mm deep, by 

erecting shuttering on the perimeter, orienting it in accordance with layout of 
your passage area; the bedding should be leveled, back-filled with gravel and 
sand, and compacted; 

  Assemble the foundation frame in accordance with Figure 2;  

  It is recommended to horizontally and symmetrically fix reinforcement rods 

600-700 mm long through holes in vertical walls of the shell 1 and shell 2;  

  Mount the assembled frame on the prepared foundation, oriented in accor-

dance with layout of your passage area; under adjustment pins put installation 
supports minimum 50 mm thick (adjust position relatively to shuttering taking 
into account concreting level);  

  Check horizontal alignment of the frame at turnstile fixing points, and if neces-

sary adjust it using gaskets and pins supplied in a standard delivery set; max-
imum allowable plane tolerance should not exceed 1,5 mm; 

  Using L-shaped installation pins and holes in shell 1 and shell 2 fix the frame 

relatively to the foundation (installation pins are not included in standard deliv-
ery set); prior to casting the frame must be properly fixed against movements 
in any direction; 

  Lay electric raceways in accordance with turnstile cables layout (Ref. Assem-

bly and Operation Manual of the turnstile) and passage area layout;  

  Fix the electric raceways relatively to the frame; ends of the electric raceways 

should be above casting level (in plates 2 – the raceway is output through 
holes designated for the indication cables; in plate 4 – the raceway is output 
through the holes designated for control and power cables); it is recommended 
to provide pulling wires to lay cables in the electric raceways in advance;  

  Outside the foundation frame the electric raceways are laid in accordance with 

the passage area layout;  

  Pour concrete to the foundation using concrete of strength class of minimum 

B22,5, up to the upper level of threaded bushes as shown in Figure 3.  
Threaded holes of the frame (fixing points of the turnstile) should be blinded 
with installation bolts to prevent concrete ingress into them during concreting.  

 

 

 

 

 

 

 

 

 

N O T E ! 

Prior to concreting the threaded holes in the frame (fixing points 

of the turnstile) must be blinded with installation bolts to pre-

vent ingress of concrete into them. 

  During concreting make sure all space of the foundation is filled with concrete, 

including space under frame itself; 

 

  Time for the concrete to set-off before the turnstile mounting is determined by 

climate conditions and concrete type. 

 

 

Summary of Contents for RTD-15 Series

Page 1: ...RF01 0 01 Certificate Foundation frame for full height rotor turnstiles of RTD 15 series...

Page 2: ...es at ambient air tempera ture from 40 to 45 and relative air humidity of up to 98 at 25 The environ ment should be free of acid and alkali vapours and gases that cause corrosion 1 6 After transportat...

Page 3: ...verall view and overall and installation dimensions are shown in Figure 1 The frame consists of 2 shells made of galvanized sheet steel and connected with fix ture plates with one another Figure 1 Ove...

Page 4: ...s recommended To perform works by at least 2 skilled workers To use installation tools hex nut wrenches S13 S17 level 5 2 Assembly Unpack the frame and check completeness of the delivery set as per Se...

Page 5: ...operly fixed against movements in any direction Lay electric raceways in accordance with turnstile cables layout Ref Assem bly and Operation Manual of the turnstile and passage area layout Fix the ele...

Page 6: ...he Product delivered are accepted by the Manufacturer in writing within no more than 5 five working days after the products are received by the Customer In case of failure to meet the abovementioned d...

Page 7: ...nufacturer s warranty obligations don t cover attendance by the experts of a Customer and maintenance of any Product on site 6 7 If in the course of the examination taken by the Manufacturer of the Pr...

Page 8: ..._ _ Date of sale ____________________201__ ____________________________________ signature seal Cutting line Warranty Repair Coupon Foundation frame RF01 0 01 for full height rotor turnstiles of RTD 1...

Page 9: ......

Page 10: ......

Page 11: ......

Page 12: ......

Page 13: ...PERCo Industrial Tel 7 812 3216172 7 812 3298924 Fax 7 812 2923608 Legal address 123 V ul Leona Pozemskogo Pskov 180600 Russia e mail support perco ru www percoweb com...

Page 14: ...www percoweb com...

Reviews: