Commissioning
2
0
1
8
-0
3
15
4
Commissioning
4.1
Introduction
Components
To commission the module, you will require the following components:
■
WCS-PG310 interface module
■
Connection cable from the interface module to the reader
■
Connector for the PROFIBUS connection to the interface module
■
PROFIBUS cable (this cable is usually already installed on site)
■
10 VDC...33 VDC power supply
GSD file (the GSD file can be obtained free of charge from our website www.pepperl-
fuchs.com)
Connecting the interface module
To ensure that the assembly functions correctly, you must carry out the following steps during
commissioning:
1. Set the PROFIBUS address on the front side of the module, using the two rotary switches
labeled "PROFIBUS ID High" and "PROFIBUS ID Low."
2. Connect the module to PROFIBUS using the interface labeled "PROFIBUS."
3. Connect the process device (reader). For information on commissioning the process device
(reader), please refer to its manual.
4. Ground the DIN mounting rail onto which the assembly is snapped.
5. Connect the direct current to the terminals provided.
6. Use any programming tool for configuration. The GSD file can be downloaded from our
website: www.pepperl-fuchs.com. Simply enter the product name or item number in the
Product/Keyword field and click the "Search" icon.
Warning!
Danger to life due to defective work
Errors during installation and commissioning can cause life-threatening injuries and significant
property damage.
■
Installation and commissioning must only be carried out by trained personnel in
accordance with the safety regulations.
Note!
The PROFIBUS address that is set must match the configured address. It is only read in when
the module is switched on.
Note!
A more detailed description of the individual steps is provided on the following pages.