●  Fit  the  pump  bracket  support  leg  and 
adjust to correct height.

● Adjust feet to the required height for the 
bath panel and slide the bath into position.

●  Set  the  bath  level  and  prefit  the  bath 
into  the  desired  position.  Check  that  the 
pump is within the confines of the bath. If 
the pump exceeds the confines of the bath 
it  will  be  necessary  to  chase  out  the  wall 
to accommodate the pump. This should be 
done before the bath is finally fitted.

● Ensure that all hot water pipes are clear 
of  the  whirlpool  pipework  -  If  necessary 
remove  bath  and  re-make  the  hot  water 
pipes keeping the blow torch away from t h e
bath and whirlpool pipework.

● When the bath is level in the required
position,  and  before  final  fixing  takes 
place,  temporarily  connect  the  waste  and 
water  feeds,  fill  the  bath  with  warm  water 
to  the  level  of  the  overflow  and  operate 
the  whirlpool  system  under  pressure  for 
a  period  of  20  minutes.  During  this  time 
all joints should be checked to ensure that 
they have not been damged or weakened in 
transit. Leave the bath standing with water 
in it for a further 20 minutes and recheck the 
joints. Carry out procedures detailed in the 
commissioning checklist opposite.

  Please  note  that  we  will  not  accept 

responsibility  for  removing  the  bath  to 
repair any leaks which are discovered after 
the bath has been finally fixed and tiled in 
place.

● The bath is now ready for an electrician to 
make the final electrical connection.

Electricians Instructions:

● The whirlpool system must be protected. 
In  most  circumstances  the  system  may  be 
connected into the 13 amp ring main, it does 
not  need  a  separate  supply  from  the  main 
board. This connection should be made via 
a 13 amp fused spur, located outside of the 
bathroom.

● It is not adviseable to locate the E.L.C.B./
R.C.C.B/  under  the  bath,  it  is  awkward  for 

access at a later date.

● DO NOT

 remove the protective tape from 

the controls on the rim of the bath until all 
plastering and grouting has been completed. 
Grout dust has been known to cement the 
air control solid.

● DO NOT

 remove any electrical ties on

the whirlpool pipework - they are there for 
a  purpose.  If  you  wish  to  relocate  any  of 
the electrical boxes for ease of access after 
installation please make sure that wires are 
not stretched.

● DO NOT

 allow anyone to dry run the pump. 

i.e.do not run the pump without water in the 
system. Water acts as a coolant for the pump 
impellor  and  casing  without  which  costly 
damage will occur.

● If it is necessary to remove the pump
from  the  bath  ensure  that  when  it  is 
reinstalled that the rubber seals are in place.

● The pump and controls have been prewired 
for ease of installation - please double check 
that all connections have travelled well and 
are to your satisfaction.

● Connect the unassigned mains cable
from the control box through the E.L.C.B. to 
the 13A fused spur.

● Connect the earth bonding as required by 
I.E.E. Regulations.

● In the absence of a plumber it is advisable 
that  the  electrician  carries  out  the  initial 
commissioning procedures - see below.

●  The  electrical  installation  should  now 
be  inspected  in  accordance  with  the 
latest  edition  of  I.E.E.  regulations  and  the 
Completion Certificate signed and handed to 
the customer.

Safety Information: 
SOP Number:
 _________________________
Pump - Serial No: ______________________
Pump Amps: _________________________
In-Line Heater Amps: ___________________

Z:\Pagemaker\Pegasus Whirlpool baths\instructions 2014\pegasus-pneumatic-user-instructions-18-03-2014.indd

Commissioning Checklist & 

Fault Finding:

1

 - Fill the bath with water to a level of 2’’ 

above the level of the jets check the system 
for leaks, please pay particular attention to 
the pump unions.

2

  -  Demonstrate  the  operation  of  the 

whirlpool to the customer.

3

 - Show the customer how to carry out the 

monthly test of the R.C.D.

4

  -  If  the  bathroom  is  to  be  tiled  after 

installation 

please 

place 

protective 

wrapping back over the controls to prevent 
contamination with grout dust.

5

  -  Hand  these  instructions,  the  electrical 

completion  certificate  and  the  system 
guarantee to the customer.

6

  -  Explain  how  the  whole  system  can  be 

isolated by means of the fused spur.

Symptom

  -  Press  on/off  button  -  nothing 

happens.

Solution

  -  Check  water  is  above  the  water 

level sensor and that the light is showing on 
the water level sensor. (Check power supply 
is getting to control box). Check operation of 
the ELCB (if fitted) if the ELCB fails to test then 
the problem is at the fuse in the fused spur. 
If power supply is getting to Control box then 
check  connections  to  pump  and  ancillarys 
are intact and have not been stressed.

Bath Waste:

Only a Pegasus whirlpool waste can be fitted 
to this bath. An upgrade bath fill waste can 
be purchased at a small extra cost (pictured 
above).

Head Office:

 61-62 Lower Dock Street, Newport, South Wales NP20 1EF

Telephone:

 (01633) 244555 

Facsimile:

 (01633) 244881

Email:

 [email protected]

Internet:

 http://www. pegasuswhirlpoolbaths.co.uk

....Continued

Reviews: