4 Assembly and installation [specialist]
14
993x053x-mub-en – V05
2020/03
1.
Take off the thermometer handles
(A-2, F-2) and remove the insulating
front shell of the HeatBloC
®
.
2.
Unscrew the nuts on the lower
connections of the HeatBloC
®
and take out the sealing rings.
If PAW modular distribution manifold
or transition connection is used:
3.
Put the two nuts over the flanges.
4.
Insert the sealing rings into the nuts.
5.
Put the HeatBloC
®
onto the two nuts.
6.
Tighten the nuts. Make sure that the
nuts do not get jammed and that the
sealing rings do not slip.
7.
Connect the HeatBloC
®
to the
installation by using the pipes.
The installation to the piping must
be carried out without any tension.
8.
Connect the pump.
9.
Carry out a pressure test and
check all thread connections.
10.
Mount the insulating front shell and
the thermometer handles (A-2, F-2).
Flange
(top view)
Nut
1
2
3
Flange
(side view)
Sealing ring