Decking Installation
Lastly, after the dock has been assembled completely, installed in the water and leveled throughout, then the pier is
ready for the decking to be installed. The most efficient way to set the decking in place is to start at the shore end of
the dock and set each panel in place, working towards the lake end. Removal is the opposite of installation.
When installing Aluminum Deck Panels, first apply the
adhesive backed Rubber Insulator to the aluminum
frames. The Rubber Insulator is installed down the length
of the
8’
Side Rails and down the length of the Center
Support Tubes.
(Only used with aluminum deck)
The Rubber Insulator is not to be installed in the di-
rection of the 4 ft. width, only lengthwise.
www.patriotdocks.com
The Cedar Deck Panel is simply set in place. The cedar panels
are sold untreated and can be installed as is. To extend the service life
of the cedar deck, a water repellant sealant can be applied (for best
results, do not use colored stain).
The Cedar Decking does not utilize a deck locker mechanism but it is
recommended that the panels be secured to the frame in some capacity.
(zip
-
ties are commonly used)
To assemble the aluminum deck
panel, lay out the deck boards, slide
stinger onto boards. Position stringer
approx.
12”
from edge. Repeat with
other stringer on opposite side.
Ensure board ends are straight,
tighten set screws to secure panel.
To assemble the poly deck panel, lay
out deck boards. Align stringer with
pre drilled hole on bottom side of
poly board. Secure with included
screw.
PN10867: Deck Locker
Use the optional Deck
Locker to secure the 4x4
’
poly deck panel onto the
dock frame.
11
-
3/4”
PN10868:
Aluminum
Deck Lockers can be
installed on the panel
to secure the decking
to the frame.
*
Sold Separately*
Stringer