12.
Insert the End Plug with new attached O-Rings into the High- Pressure
Vessel while aligning the High-Pressure Port and Product Water Port to
the respective holes in the High-Pressure Vessel. Continue pushing
inward on the End Plug until its exposed end travels just past the
Segment Ring Groove in the Pressure Vessel. Ensure that the Ports of
the End Plug are aligned with the Port Holes of the High-Pressure
Vessel.
13.
Screw in fitting connectors.
14.
Insert the three-piece Segment Ring Set into the Segment Ring Groove
of the High-Pressure Vessel. Align the Segment Ring Set with the
tapped holes in the End Plug for insertion of the three SC SOC CAP
1/4-20 X 3/4 SS #5. Attach the three SC SOC CAP 1/4-20 X 3/4 SS #5
and tighten.
15.
Reconnect the Hoses to the respective fitting on the Pressure Vessel.
16.
After the membrane element has been changed, operate the RO unit
and check for leaks.
5.4
INSPECTION LOG
Figure 5.2 depicts a Sample Operational Log for the RO unit. The operator of the RO
unit should establish a program for entering the required data on a regular basis.
Maintaining accurate operational data is the first, and most important, step in
determining preventative maintenance requirements and reducing system
downtime. Figure 5.3 depicts a Sample Discrepancy Report that may be used for
reporting and tracking problems with the RO unit.