Release 1.01 

Office

, man-portable, self assembly type EC1.1 

 

 

 

 

 

14)

Fit the ceiling panels. 

(Fig. 21)

15)

These fit on the top of the retention bars
and slot together like the wall panels

Fig. 21 

Fig. 24 

16)

Slide on the roof panels. Take care to
ensure the lip locates correctly where the
two halves connect.

(Fig. 24 & 25).

17)

Fit the centre roof cap with 13mm bolts &
washers. 

(Fig. 26 & 27).

Fig. 25 

Fig. 26 

Fig. 27 

Fig. 22 

18)

Fit the roof fascia to both long sides.

(Fig. 28).

19)

Fit the bolts into the four corners. 

(Fig.29).

Congratulations 

– you have completed your 

office

Fig. 29 

18) Weather seal the inner roof 

(Optional - but recommended

)

Use the supplied silver waterproofing tape to seal between all
joints on the roof. This forms a second line of defence for extreme
weather conditions, we recommend it is applied as
follows:

a) Between roof panels 

(Fig. 22)

b)

All around the edge of the roof panels where they meet the ceiling
retention bar. 

Tip: Lap the tape over the ceiling panel and down over the

ceiling retention bar. This prevents capillary action in extreme weather
conditions.

c)

Pay particular attention to the corners of the roof frame. 

(Fig. 23)

Fig. 23 

Fig. 28 

Summary of Contents for XPANDAOFFICE

Page 1: ...Release 1 01 Office man portable self assembly type EC1 1 assembly instructions XPANDAOFFICE ...

Page 2: ...ound 2 Remove the four packing posts using a 19mm spanner Fig 2 3 3 Remove the four bolts on the corners of the unit using a 13mm spanner Fig 4 4 Remove the roof fascia cover on both sides Fig 5 6 5 Remove the roof connector 4 x 13mm bolts Fig 7 8 Fig 1 Fig 2 Fig 3 Fig 4 Fig 5 Fig 6 Fig 7 Fig 8 ...

Page 3: ...ig 10 Fig 11 Fig 12 Fig 13 8 Remove the plastic film from all panels Fig 14 9 Starting with the short side slot a narrow wall panel into the corner post slot cut side toward post Then two full panels door blank panels as required 10 Fit another internal and external corner post 11 Fit panels as before Continue until all four walls are fitted Fig 15 16 17 Fig 14 Fig 15 Fig 16 Fig 17 12 Fit the ceil...

Page 4: ...into the four corners Fig 29 Congratulations you have completed your office Fig 29 18 Weather seal the inner roof Optional but recommended Use the supplied silver waterproofing tape to seal between all joints on the roof This forms a second line of defence for extreme weather conditions we recommend it is applied as follows a Between roof panels Fig 22 b All around the edge of the roof panels wher...

Page 5: ...ute the lifting eyes Fig 28 for the supplied connection brackets Fig 29 as shown to provide secure stacking Fig 27 Fig 28 Fig 29 Fig 30 Thank you for purchasing this unique building XPandaOffice can be linked together to form a modular building by using a simple linking kit Also available windows guards electric packs forklift tunnels and replacement panels Contact your dealer for more information...

Reviews: