E. Rotate the Main Cam Gear counter-clockwise again (
Fig. S9
) to
remove the cassette-tape as shown in
Fig. S7
.
F. Set the Position Switch to EJECT POSITION certainly as shown
in
Fig. S10
.
Fig. S10
G. Install the Loading Motor and tighten screw (S1) as shown in
Fig. S8
.
2.4.4. CYLINDER UNIT REPLACEMENT
NOTE:
Replacing only Upper Cylinder unit of R4 Mechanism cannot be performed, as securing of RT
gap is impossible out of factory, please replace the cylinder by whole Cylinder Unit. The
Compatibility Adjustment should be performed after replacement ofthe DD Cylinder Unit.
1. Remove the Mechanism Unit from Main C.B.A./Chassis by
referring to "Disassembly Procedure".