5.2.12.1. Reassembly Notes
1. Installation/Alignment of Intermediate Gear A, Lift Gear and P5
Arm Unit
A. Rotate the Lift Gear so that Hole A on Lift Gear is a Through
Hole with a hole on chassis.
B. Install the Intermediate Gear A so that the hole on Intermediate
Gear A is aligned with the hole on Lift Gear.
C. Install the P5 Arm Unit so that it contacts with the tab of
chassis.
Fig. J10-2
2. Installation of Opener Piece
A. Install the Opener Piece so that the slot of the Opener Piece is
inserted to the Pin of Pinch Arm Unit
Fig. J10-3
5.2.13. Motor Block Unit, Audio Control Head Unit, Lift Gear, Tension Arm Boss,
and Cleaner Arm Unit
Fig. J11
34
Summary of Contents for NV-FJ6140PN
Page 6: ...Fig 1 4 Fig 1 5 6 ...
Page 19: ...Figure 19 ...
Page 24: ...5 2 3 EJECT Position Confirmation Fig J1 2 24 ...
Page 35: ...5 3 CASSETTE UP ASSEMBLY SECTION 5 3 1 Top Plate Wiper Arm Unit and Holder Unit Fig K1 1 35 ...
Page 50: ...10 2 MECHANISM BOTTOM SECTION 50 ...
Page 51: ...10 3 CASSETTE UP COMPARTMENT SECTION 51 ...
Page 52: ...10 4 CHASSIS FRAME AND CASING PARTS SECTION 52 ...
Page 53: ...10 5 PACKING PARTS AND ACCESSORIES SECTION 53 ...