Installation of the ducts

 

Use the tapping screws included with the 

   

ducts to mount the ducts directly to the ceiling(or wall).

Use all of the mounting holes.

Screw one screw partway in, fit the elongated hole of

the duct onto that screw, and then screw the other 

screw in through the round hole in the duct. This allows 

the installation to be completed by one person.

Mounting the pipe-suspended hangers 1

Use this procedure if the Factory Line 20 ducts 

are to be suspended from pipes, If necessary, the 

pipes can be shortened to the required length by 

cutting them at the flange end.

The standard interval for mounting of the hangers is 1 m, and the maximum 

   

interval is 1.5 m. Be sure to mount securely to a structural member.

Flange mounting dimensions

Flange

Standard 1 m, maximum 1.5 m

Pipe-suspended hanger

Factory Line 20 duct

Structural

member

Ceiling

materialt

66.7

Installation the flanges

the pan head

machine screw

 figure 1

Pipe mounting hole

Flange

Securing screw

Flange cover

Dismount

figure 2

Mount

Adjust the length the pipe-suspended hangers after mounted

In order to adjust the length after the pipe-

 

suspended 

hangers have been mounted to a structural member,

loosen the securing screw, remove the pipe, and cut 

the pipe at  the flange end.

After cutting, drill a hole 

(

φ

5.5 mm), mount the 

flange, and then mount a 

pipe to the flange.

Unit : mm

Mounting the ducts directly to the ceiling

Support spacing for the duct

1.

Turn the flange cover to the left to remove it.

2.

Use the wood screw or tapping screw ,then mount the flange to a 

structural member.

3.

Align the pipe mounting hole of the pipe suspension  hanger with the 

position of the pan head machine screw to put the pipe in the flange, 

and then fasten the pan head machine screw and the setscrew. 

(Fasten the pan head machine screw through the pipe mounting hole.)

4.

Turn the flange cover to the right to mount it back in its 

original position. 

Ensure the strength of building structures enough to support 

the hanging weight (a maximum of 10kg per support).

 Not doing so may cause the hanger to drop.

Use two or more pieces of hanger for one duct.

 I It will become a cause of fall if it does not so.

To prevent the ducts from meandering, align the hanger centers.

 Not doing so may cause the hangers to drop.

Caution

Securely fasten the wood screw or tapping 

screw, pan head machine screw, and setscrew.

Caution

Notes

● 

Do not attach the plug unit with the place where  

the tapping screws were mounted.

Round hole

Elongated hole

Screw in

 partway.

Screw

Duct

250

250

500

250

750

250

750

1000

750

Round hole

(Mounting hole)

Elongated hole

L=1m

L=2m

L=3m

250

21.5

φ

5.5

Fix the duct to building structure firmly.

It will become a cause of fall if it does not so.

Caution

Instllation Procedure

33

17

1919

Ceiling

Tapping screw(4×25)

4

Summary of Contents for Factory Line 20

Page 1: ...your electrical worker to take necessary actions In such case be sure to pass Instruction and Installation Manuals Not doing so will result in an electric shock a fire or a drop Use the rated voltage within the load capacity that is always displayed Not doing so will result in a fire Use Fluorescent lighting plug below a permissible load Not doing so will result in a fire or a drop Caution this pr...

Page 2: ...he smoke rises The place which is subject to the influence of heat such as the upper part of a heater Not doing so will result in an electric shock a fire or a drop Do not install the Factory Line duct passing through building structure Doing so may result in a fire Do not slide putting the plug in the duct Poor contact will cause a fire During construction Do not give a shock such as dropping on ...

Page 3: ...ceiling side directly Are there loose the screw Retighten Are there discoloration or deformation in the plastic of the duct and Change it Are there adhesion and deposition of dust in the inside of a duct Remove the dirt Is a straight line connecting duct Attachment is improved so that it may become a straight line Is the thing which is not an exclusive plug attached to the duct Exchange plugs The ...

Page 4: ... mm mount the flange and then mount a pipe to the flange Unit mm Mounting the ducts directly to the ceiling Support spacing for the duct 1 Turn the flange cover to the left to remove it 2 Use the wood screw or tapping screw then mount the flange to a structural member 3 Align the pipe mounting hole of the pipe suspension hanger with the position of the pan head machine screw to put the pipe in the...

Page 5: ...via the pipe suspended hangers method for bringing in the power supply Route the cable from the ceiling into the pipe When doing this it is easier if the cable is passed through the pipe before securing the Factory Line 20 duct in the hanger Following the same procedure for Step fit the duct in the hanger and then fix it with the cap Use single conductor cables of 1 6 or 2 0 m in size Make wire co...

Page 6: ... duct into the hanger and then turn the cap to the right and tighten the securing screw in order to secure the duct Ensure the strength of building structures enough to support the hanging weight a maximum of 10 kg per support Not doing so may cause the hanger to drop To use long hanger bolts mount these bolts using sway braces Use two or more pieces of hanger for one duct It will become a cause o...

Page 7: ...rew During construction Do not give a shock such as dropping on a product or hitting It may be damaged Combine the tip of a duct and connect certainly Connect a straightly both of the duct Securely fasten the set screws Proper torque 0 98 N m 1 32 N m Doing so may result in an electric shock or a fire When cutting the ducts use a metal hacksaw hand type and cut with the opening in the duct facing d...

Page 8: ...y cable of the grounded side to the Polarity indication ground side the terminal screw of which is plated Caution Set screw Polarity indication ground side Polarity indication ground side Duct Duct Grund terminal M4 Terminal screw plated To connect the duct with the center feed in joiner be sure to align the Polarity indication ground side with each other Only to make connection the cover needs no...

Page 9: ...ng so may result in a fire Do not slide the plug with having come in the duct Doing so may result in faulty connection thus leading to a fire Caution Notes Do not attach the plug unit where the tapping screw is used the duct directiy Notes Do not attach the plug unit where the tapping screw is used the duct directiy 1 2 3 4 5 Do not slide the plug with having come in the duct Doing so may result in ...

Page 10: ...g the lever duct outlet plug lever lock Notes Do not attach the plug unit where the tapping screw is used the duct directiy Do not slide the plug with having come in the duct Doing so may result in faulty connection thus leading to a fire Caution 13 Mounting an electrical outlet plug Mounting plug Matching the polarity indications on the duct and the plug insert the plug into the duct and rotate it...

Page 11: ...ut Fluorescent lighting plug Power supply hole Locknut Mounting fluorescent lighting fixture to the duct fluorescent lighting plug and clamp lever handling method To mount Rotate clockwise until the lever no longer rotates To dismount Rotate counterclockwise until the lever no longer rotates To connect the cable to unthreaded terminal use bar type crimp style terminal Not doing so may result in fault...

Page 12: ...oster might discolor and begins to burn because of the heat of the illuminator Caution Duct Opening Duct cover Use the poster clip to suspend a work instruction sheet or process chart from the Factory Line 20 Fold down about 10 mm of the top of the work instruction sheet or process chart and slide it sideways into the poster clip The work instruction sheet can be positioned in the desired directio...

Reviews: