Continue  the  installation  of  the  walls  by  strongly  forcing  the  wall  logs  into  one  another.  If  necessary, 
use the hitting block and hammer. At the same time, do not forget to begin the installation of the door 
and windows. You should definitely begin the door installation after the 5

th

-6

th

 layer of logs. 

Door and window 

Doorframe: 

  If  it  is  a  double  door,  the 

doorframe 

is 

supplied 

in 

separate 

parts 

due 

to 

transportation  requirements  and 
you  will  have  to  begin  by 
assembling it.  

  To  do  this,  place  together  the  4 

parts  of  the  frame  and  screw 
them onto one another.  

  Make  sure  that  the  part  of  the 

frame  with  the  deeper  notch  is 
installed  upwards.  The  lateral 
jamb  parts  have  hinges  and  are 
mirrored.  

  It  is  recommended  to  install  the 

leaves later.  

  If it is a single door, its frame and 

leaf 

are 

supplied 

already 

assembled. 

 Doorframe installation (Only necessary for a double door!): 

 

 

Door installation: 

The  doorframe  is  placed  at  the 
formed  aperture  and  pushed  with 
force  onto  the  lower  log.  If  it  is  a 
double door, place  the leaves on the 
hinges  now.  To  open  and  close  the 
door, fit the separately packaged lock 
and handle.  

 

 

 

Window installation: 

Continue  with the  installation  of the  wall  logs until  you reach the  window height. The  wall plans (see 
Technical specifications) show how many  logs go under the window. Install the window  similarly with 
the door. Just like the door, push the window frame with the window into the window aperture onto the 
lower log, applying force. Make sure that the window is not fitted backwards (topsy-turvy).  

ADVICE

:  Definitely  make  sure  that  the  windows  and  doors  open  in  the  proper  direction.  The  doors 

always open from the inside 

to the outside

. The tilt&turn windows open 

to the inside

. The revolving 

and the slinging windows open 

to the outside

 (the window handles are on the inside). 

ATTENTION

: It is not necessary to fix the doors and windows to the wall logs! If you wish to do this, it 

will be sufficient to fix them with a couple of screws in the lower part of the frame because as they dry, 
the wall logs will begin subsiding.  

You can conduct the final adjustments of the doors and windows only some 2-3 weeks after the house 
installation, when the house will have become adapted to weather conditions and its logs settled.  

 

Summary of Contents for FRG34-5038

Page 1: ...ompte En cas d une réclamation veuillez respecter le déroulement suivant il vous faudra présenter à votre commerçant agréé ce bulletin de contrôle avec le récépissé de l achat Ce ne sera que moyennant présentation de ces documents qu un traitement rapide et sans problème de votre réclamation sera possible Italiano Il prodotto che avete acquistato è stata prodotta secondo la norma di alta qualità I...

Page 2: ...rodukto įsigijimo vietą turite pristatyti apžiūros pažymėjimą bei pirkimo kvitą Tik tais atvejais kai pristatomi minėti dokumentai pretenzija gali būti nagrinėjama greitai ir be komplikacijų Polski Produkt który Państwo zakupili wykonano według najwyższych norm jakości Elementy konstrukcyjne przed zapakowaniem przeszły dokładną kontrolę jakości Aby uniknąć problemów podczas samodzielnego montażu b...

Page 3: ...dor Ostja aadress Telephone Telefoon Telefon Téléphone Teléfono Telefon Telefon nr Puhelin Telefon Telefon Tālrunis Telefonas Telefon Telefone Telefon Forwarder Pick up Others Door Verzending Zelf Afhalen Spedition Selbstabholer Par Transporteur Propres moyens Tramite Spedizioniere Mezzo proprio Entrega Transporte organizado transporte propio Transportør Sendes Hentes Transportør Sendes Hentes Rah...

Page 4: ...ndre tekniske egenskaper ved produktet Alle rechten en technische wijzigingen voorbehouden Installation manual Montageanleitung Notice de montage Istruzioni per il montaggio Manual de montaje Monteringsanvisning Installatiegids Log cabin FRG34 5038 Blockhaus Maisonnette en poutres Casa di travi Casa de jardin Anneks Tuinhuis Width 500 x Depth 380 cm Breite Tiefe Largeur Profondeur Lunghezza Profon...

Page 5: ...360 474 480 520 16 7m ...

Page 6: ......

Page 7: ...BOX ...

Page 8: ......

Page 9: ......

Page 10: ......

Page 11: ......

Page 12: ......

Page 13: ......

Page 14: ......

Page 15: ......

Page 16: ...mber of the house We can only review complaints if you submit the control number of the house to the seller The warranty does not cover Peculiarities of wood as a natural material Wooden details already painted processed with a wood preservative Wooden details containing whole branches that do not endanger the stability of the house Colour tone variations caused by wood structure differences that ...

Page 17: ... and windows with a wood impregnation agent and do that namely both inside and outside Otherwise the doors and windows can become twisted After the house assembly is completed we recommend for the conclusive finishing a weather protection paint that will protect wood from moisture and UV radiation When painting use high quality tools and paints follow the paint application manual and manufacturer ...

Page 18: ...e foundation so that its upper edge extends from the ground to a height of at least 5 cm At the same time make sure that there are sufficient air apertures under the house floor for ventilation We recommend the following foundation options Strip or spot foundation Foundation from concrete or pavement slabs Cast concrete bed Prepare the foundation so that the foundation joists are propped up on eve...

Page 19: ...he corresponding materials are not included in the supplied kit Installation of foundation joists Walls When installing the walls it is important to remember that The logs are always assembled with their tongue upwards If necessary use the hitting block and hammer Never directly hit the tongue with the hammer Install the walls in accordance with the appended wall plans see Technical specifications...

Page 20: ...ace the leaves on the hinges now To open and close the door fit the separately packaged lock and handle Window installation Continue with the installation of the wall logs until you reach the window height The wall plans see Technical specifications show how many logs go under the window Install the window similarly with the door Just like the door push the window frame with the window into the wi...

Page 21: ...ary or plane the apex or sidewall log somewhat lower Roof Before installing the roof boards make sure that the house is completely level Use the water level to check all walls ATTENTION When placing the roof use a stable ladder Do not step on the roof as the structure is suitable to sustain only an even load snow wind etc and not a point load Begin the installation of the roof boards from the fron...

Page 22: ...ards with the supplied felt nails at intervals of about 15 cm Make sure that the felt strips overlap by at least 10 cm Having installed the roof cover material attach the wind braces to the roof and the facia boards to the purlins and upper wall logs Installation of wind braces and facia boards Floor Only when the house is built completely you can install the floor boards thus avoiding unnecessary...

Page 23: ...cessary shorten the upper ends of the slats Do not turn the screws tightly so wood can further swell or diminish With the house having settled you should adjust the attachments so the wall logs can settle Installation of storm braces General advice Problem Gaps appear between the wall logs Cause Additional details are attached to the house that do not allow wood to swell diminish Solutions If the ...

Reviews: