4.2.3.1
Connecting the 3-phase supply cable to the power box
If it is necessary to connect the 3-phase supply cable to the power box, use the following
steps.
1)
Ensure that the supply cable is not connected to the safety isolation box.
2)
Remove the power box cover.
3)
Inside the power box, remove the clear plastic safety cover from the power box
(secured to the right-hand side of the power box by four screws).
4)
Connect the 3-phase supply cable wires as shown in Fig 4-1.
5)
Re-fit the clear plastic safety cover and then the power box cover.
L1
L2
L3
Neutral
Protective
Earth (at
side of
panel)
Connection
Terminal for
Earth cable to
Gas Pod
3-phase connections
Clear plastic
safety cover
Fig 4-1: 3-phase supply cable connections at the power box
Installation and Commissioning
Printed: 14 July 2010 08:27
Page 4-5 of 8
Issue 8: July 10