12
OB SLAVE L1
With the Port 01 FX as the master, press the
<PORT>
soft key to change the remaining Ports and
designate the remaining inverters as slaves. To designate them as OB SLAVE L1 for a paralleled system,
follow the instructions below. To program them as slaves in a three-phase system, proceed to the next
page.
The MATE screen for Port 02 will look like this:
ADV/FX/STACK--------P02
stack Master
phase
DOWN INC DEC PORT
• Press the
<PORT>
soft key to select the second
inverter on the HUB.
• In the example to the left, t
he MATE is now ready to
program the FX plugged into Port 02 of the HUB.
• Please note that Master is the factory default
value for the FX inverter. each non-master FX
inverter must be programmed accordingly.
ADV/FX/STACK---------P02
stack Classic Slave
phase
DOWN INC DEC PORT
• Press the
<INC>
soft key. This will advance the
display to the Classic Slave screen.
Please note that
the International Series GTFX and GVFX cannot
utilize Classic Slave mode.
Press the
<INC>
soft
key again until the display reads OB Slave L1.
• If you have more than two inverters, push the
<PORT>
soft key to advance to the inverter on
P03 (or the next port on the HUB). Once you have
selected the next inverter, press the
<INC>
soft key
to advance the display to OB Slave L1.
Note:
There are no
<OK>
or
<DONE
> commands in the stacking menu. Whichever value—Master
or Slave — shows up on the MATE screen will be assigned to the chosen Port (and FX) upon leaving
that screen. It’s important to watch the Port number in the top right corner of each screen to be sure
you’ve assigned it the desired status.
ADV/FX/STACK---------P03
stack OB Slave L1
phase
DOWN INC DEC PORT