Connect AC Power Cables Before Installing Tool-less Slide-Rails in Sun Rack II 1042
Connect AC Power Cables Before Installing Tool-less Slide-
Rails in Sun Rack II 1042
Note -
You must perform the procedure in this section if you are installing the storage server in
the Sun Rack II 1042 (1000-mm) system rack. This procedure does not need to be performed if
you are installing the storage server in the Sun Rack II 1242 system rack.
Right-angle AC power cables must be installed before slide-rails when installing the storage
server into a Sun Rack II 1042 (1000-mm) system rack. The standard rail kit tool-less slide-rails
impede access to the 15kVA and 22kVA Power Distribution Unit (PDU) electrical sockets in the
1000-mm rack. If you use the standard AC power cables and then install the slide-rails into the
rack, you will be unable to disconnect or remove the AC power cables.
You must use the following 2-meter right-angle AC power cable for this procedure:
■
7079727 - Pwrcord, Jmpr, Bulk, SR2, 2m, C14RA, 10A, C13
Installing the Storage Server Into a Rack
33
Summary of Contents for EXADATA X6-2
Page 2: ......
Page 8: ...8 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 14: ...14 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 24: ...24 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 60: ...60 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 66: ...66 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 70: ...70 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...