1-3-2
BDP_ISP
Safety Check after Servicing
Examine the area surrounding the repaired location
for damage or deterioration. Observe that screws,
parts, and wires have been returned to their original
positions. Afterwards, do the following tests and con-
firm the specified values to verify compliance with
safety standards.
1. Clearance Distance
When replacing primary circuit components, confirm
specified clearance distance (d) and (d’) between sol-
dered terminals, and between terminals and surround-
ing metallic parts. (See Fig. 1)
Table 1 : Ratings for selected area
Note:
This table is unofficial and for reference only.
Be sure to confirm the precise values.
2. Leakage Current Test
Confirm the specified (or lower) leakage current
between B (earth ground, power cord plug prongs)
and externally exposed accessible parts (RF termi-
nals, antenna terminals, video and audio input and
output terminals, microphone jacks, earphone jacks,
etc.) is lower than or equal to the specified value in the
table below.
Measuring Method (Power ON) :
Insert load Z between B (earth ground, power cord
plug prongs) and exposed accessible parts. Use an
AC voltmeter to measure across the terminals of load
Z. See Fig. 2 and the following table.
AC Line Voltage
Clearance Distance (d), (d’)
110-240 V
≥
3 mm(d)
≥
6 mm(d’)
Fig. 1
Chassis or Secondary Conductor
Primary Circuit
d'
d
AC Voltmeter
(High Impedance)
Exposed Accessible Part
B
One side of
Power Cord Plug Prongs
Z
Fig. 2
Table 2: Leakage current ratings for selected areas
Note:
This table is unofficial and for reference only. Be sure to confirm the precise values.
AC Line Voltage
Load Z
Leakage Current (i)
One side of power cord plug
prongs (B) to:
110-240 V
2k
Ω
RES.
Connected in
parallel
i
≤
0.7mA AC Peak
i
≤
2mA DC
RF or
Antenna terminals
50k
Ω
RES.
Connected in
parallel
i
≤
0.7mA AC Peak
i
≤
2mA DC
A/V Input, Output
Summary of Contents for DV-BD606 - Blu-ray Single Disc Player
Page 3: ...1 1 1 E5J50SP SPECIFICATIONS...
Page 26: ...1 9 4 AV 2 3 Schematic Diagram E5J50SCAV2...
Page 27: ...1 9 5 E5J50SCAV3 AV 3 3 Schematic Diagram...
Page 29: ...1 9 7 Front Power SW Schematic Diagram E5J50SCF...
Page 30: ...1 9 8 SD Schematic Diagram E5J50SCSD...
Page 33: ...1 9 11 FE Main 3 5 Schematic Diagram E5J50SCFM3...
Page 44: ...1 9 22 BE Main 9 10 Schematic Diagram E5J50SCBM9...
Page 45: ...1 9 23 BE Main 10 10 Schematic Diagram E5J50SCBM10...
Page 46: ...1 9 24 AV CBA Top View BE5J10F01072A...