INDICATION OF USE

Oleo buffers are supplied with a standard finish for dry
conditions. The standard finish is not suitable for wet or
corrosive conditions such as mineshafts etc.

Environmental temperature acceptable conditions: -15°C
to 70°C

Note: for special conditions outside the above consult
Oleo International.

Buffers are to be fitted vertically parallel to guide rail 
+/- 5 mm. For non vertical applications please consult
Oleo International.

PREPARATION FOR INSTALLATION

The Oleo elevator buffer is supplied with a sealed gas
precharge; the plunger is held in the fully compressed
condition during transportation by means of a transit eye
bolt. The transport eye bolt and spacer must be removed
but the adaptor must remain in the delivered position,
the plunger must be allowed to extend fully. The following
is the recommended removal procedure.

Before fitting buffer isolate the lift car while working
underneath.

Before the buffer is released ensure that there is
sufficient clearance to allow full extension. Do not stand
over the buffer.

Use appropriate lifting equipment for designated weight
of buffer, do not lift the buffer using the plunger; use the
lifting eye bolt.

Weight of buffer is shown in table 1.

Undo and discard the eye bolt and spacer but leaving
the adaptor in the delivered position as per diagram on
page 2.

The units will require filling with oil to the specified level
as per the oil filling procedure.

At installation the correct oil level of all buffers must
be checked.

Make electrical connections to the limit switch.

NOTE: For base fixing-minimum rawl bolt depth in floor
should be 130 mm bolt shank diameter 16 mm.

The maximum overall height should be checked
against table 1 and should be 0/- 9.5 mm of the
figure stated.

OIL FILLING PROCEDURE

The filling can be either before or after installation of the
buffer but the correct level must only be checked when
extended. The buffer must be vertical when filled. 

The correct oil specification is listed on the data label: 

a) Securely mount the buffer in the shaft bottom.

b) Remove oil filler plug and dipstick, as per instructions

on page 15.

c) Fill the unit with oil if necessary, the approximate

volume is stated in table 1. The filling location is as per
the instructions on page 15.

d) Take care when handling the oils. Observe the oil

manufacturers recommendations.

e) Allow to stand for 30 minutes, then check oil level

with dipstick when buffer is fully extended and top up
as necessary. Leave to stand for a further 20 minutes,
recheck and top up again if required. The oil must be
at the level indicated on the dipstick.

f) If possible compress the plunger, then release – observing

that full extension is smoothly attained.

g) Refit oil/filler/dipstick.

MAINTENANCE

Inspection need be no more frequent than the local
statutory checks on elevator installations or following an
impact. At the time, it is only necessary to simply check
that the oil level is correct and that the overall height
remains to the correct measurement. After impact check
buffer visually for any damage. Check gas spring by making
sure the buffer has fully re-extended.

Remove and clean away any dirt and debris around the
plunger and switch. Check the alignment of the striker,
this should be parallel with the plunger and switch, in a
vertical position.

NOTE: If the buffer has not returned to the fully
extended position (determined by measuring overall
height) contact the buffer supplier.

OIL SPECIFICATION

The oil must conform to the specification on the buffer
data plate – ISOVG68 – SG.88/.90 at 15°C – hydraulic. 

Pour Point -18°C or lower. Viscosity index 75 or higher.

Summary of Contents for LB 16-40

Page 1: ...E LE VATO R LB 16 40 INSTALLATION GUIDE GUIDE D INSTALLATION MONTAGEANLEITUNG GUIDA ALL INSTALLAZIONE GU A DE INSTALACI N GUIA DE INSTALA O...

Page 2: ...inf llverschluss Messstab Tappo olio asta di livello Varilla medidora llenado aceite Vareta de enchimento do leo Adaptor Adaptateur Adapter Adattatore Varilla medidora Ilenado aceite Orif cio de escap...

Page 3: ...against table 1 and should be within 0 9 5mm of the figure stated OIL FILLING PROCEDURE The filling can be either before or after installation of the buffer but the correct level must only be checked...

Page 4: ...au 1 la tol rance au chiffre indiqu tant de 0 9 5 mm PROCEDURE DE REMPLISSAGE D HUILE Le remplissage peut tre effectu avant ou apr s l installation de l amortisseur mais le niveau ne peut tre v rifi q...

Page 5: ...etragen Die maximale L nge ber alles sollte gepr ft und mit den Angaben in Tabelle 1 verglichen werden Toleranz 0 9 5mm gegen ber den Angaben F LLEN MIT L Die F llung kann vor oder nach der Montage er...

Page 6: ...ompresa tra 0 9 5mm del valore indicato PROCEDURA DI RIEMPIMENTO DELL OLIO Il riempimento pu essere eseguito sia prima sia successivamente l installazione dell ammortizzatore ma il livello corretto de...

Page 7: ...CEITE El llenado puede realizarse antes o despu s de la instalaci n del amortiguador pero el nivel de aceite solo debe comprobarse cuando est extendido El amortiguador debe estar en posici n vertical...

Page 8: ...e acordo com a tabela 1 e deve corresponder entre 0 9 5 mm do valor indicado PROCEDIMENTO DO ABASTECIMENTO DE LEO O abastecimento pode ser feito antes ou depois da instala o do amortecedor mas o n vel...

Page 9: ...O LE O I NTE R NATI O NA L 9 LB 16 40 Oleo 15 C 7 0 C Oleo 5 mm Oleo Oleo I I 130mm 16mm I 0 9 5 mm a b c I d e 30 20 f g ISO VG68 SG 88 90 15 C 18 C 75...

Page 10: ...LB 16 40 10 Oleo 15 C 70 C Oleo 5mm Oleo Oleo 1 2 130mm 16mm 1 0 9 5mm a b 15 c 1 15 d e 30 20 f g ISOVG68 SG 88 90 AT 15 C 18 C 75...

Page 11: ...O LE O I NTE R NATI O NA L 11 LB 16 40 Oleo 15 C 70 C Oleo International 5mm Oleo International Oleo 1 2 130mm 16mm 1 0 9 5mm 15 1 15 30 20 15 C ISOVG68 SG 88 90 18 C 75...

Page 12: ...LB 16 40 12 Oleo 15 C 70 C Oleo International 5 Oleo International Oleo 1 1 130 16 1 0 9 5 a b c 1 d e 30 20 f g ISO VG68 SG 88 90 15 C 18 C 75...

Page 13: ...ales lvolumen Volumen de aceite nominal Volumen nominal de aceite Volume Nominal de leo Buffer Mass No Oil LB 16 203mm 7 99in 617 3mm 24 32in 4 62 litres 24 0kg LB 18 249mm 9 80in 723 3mm 28 45in 5 58...

Page 14: ...ge en place pour le transport 1 Pegelstab f rTransport montiert 1 Asta di livello montata per il trasporto 1 Varilla medidora montada para transporte 1 Vareta adequada para transporte 1 1 1 1 2 Lift o...

Page 15: ...or 4 Puxe a vareta para baixo at ao fim do buraco de maneira que a extremidade da haste entre na placa superior 4 4 4 4 5 Image shows dipstick correctly fitted buffer ready for service 5 L illustratio...

Page 16: ...xhall Coventry CV7 9NE UK T 44 0 24 7664 5555 F 44 0 24 7664 5900 E sales oleo co uk OLEO CO UK W E P R OV I D E S O LU T I O N S N OT J U ST P R O D U CTS 1 29192 1 Issue 1 March 2015 EUROPE CANADA U...

Reviews: