LED ELEVATED HELIPORT LIGHT LHE 
INSTRUCTION MANUAL FOR USE, INSTALLATION AND MAINTENANCE 

 

 

3.2

 

 INSTALLING THE LIGH UNIT 

The  light  is  shipped  completely  assembled  including  the  LED  module,  except  the  1-
inch tube and the breakable coupling which are delivered separately inside the same 
carton. 

Note: 

if the fixture has been ordered with an extra height option, the tubing may be 

packaged separately. 

For the installation of the light the following steps are suggested: 

 

pass  together the  secondary  cable  lead  with  receptacle  and  a  suitable length  of 
grounding wire (grounded inside the pit) through the pipe elbow 

 

place  the  receptacle  into  the  upper  threaded  section  of  the  pipe  elbow,  by 
holding it between the two plastic rings, and pass the grounding wire through the 
rings (in correspondence of break point provided on the rings) 

 

slide one end of the 1-inch tube over the fixture cable assembly (cable leads with 
plug  plus  yellow-green  wire)  and  into  the  fixture  body  until  the  body  bottoms 
against the tube 

 

approach,  without tighten, the  set  screws  on the  side  of the  body to the  1-inch 
tube 

 

slide  the  frangible  coupling  over  the  cable  assembly  (cable  leads  with  plug  plus 
yellow-green  wire)  and  onto  the  other  end  of  the  1-inch  tube  until  it  bottoms 
against the tube 

 

connect the fixture grounding wire to the grounding wire coming from the pit (or 
from  the  base):  splice  both  the  wires  and  connect  them  together  by  using  a 
crimping connector 

 

connect the light plug to the secondary receptacle inside the pipe elbow 

 

slide the frangible coupling down over the plug and tighten it into pipe elbow (or 
the base plate) until coupling bottoms out. Push any extra cable length into the 1-
inch tube. Tighten the tube to the coupling with the setscrew on the coupling 

 

Place  on  the  lens  locking  ring  the  levelling  device  (P/N  332.3500  available  on 
request)  as  shown  in  Figure  5.  Levelling  the  light  body  by  operating  the  three 
levelling screws until the bubble is centered 

 

remove the levelling device 

 

 

 

 

Summary of Contents for LHE

Page 1: ...IVERED BY MEANS OF THE AUTOMATIC KNOWLEDGE MANAGEMENT SYSTEM IT CAN BE SIGNED ON REQUEST THIS DOCUMENT AND THE DATA CONTAINED HERE IN IS PROPRIETARY PROPERTY AND SHALL NOT BE DUPLICATED USED OR DISCLO...

Page 2: ...the applicable warranty period All costs of transportation of Products claimed not to be warranted and of those repaired or replaced to or from the facility of the Company shall be borne by Purchaser...

Page 3: ...he unit opened the main circuit breaker and removed the supply to the unit by opening the circuit breaker switch on the distribution board at the beginning of the supply line Then wait discharge time...

Page 4: ...AND MAINTENANCE EDITIONS Date 02 10 2013 11 14 2013 11 03 2014 First issue Updated chapter Cable lead with plug and List of the recommended spare parts New address of the Company Deleted List of the...

Page 5: ...4 1 1 Periodical Checks 13 4 1 2 Snowplow Operations 13 4 2 REMOVING AND OPENING THE LIGHT UNIT 13 4 2 1 Removing the fixture 13 4 3 LENS CLEANING 13 4 3 1 Prism outside cleaning 13 4 4 LENS REPLACEME...

Page 6: ...EN Page 6 of 17 Edition 11 03 2014 Supersedes edition 11 14 2013 LED ELEVATED HELIPORT LIGHT LHE INSTRUCTION MANUAL FOR USE INSTALLATION AND MAINTENANCE LIST OF ATTACHMENTS UC PU 0279 LIST OF THE RECO...

Page 7: ...the pole using three screws These screws also allow the levelling of equipment the power supply control PCB and the LED circuit are mounted on the aluminium inner body steel 1 inch tube available in...

Page 8: ...Document UT MT 0708_EN Page 8 of 17 Edition 11 03 2014 Supersedes edition 11 14 2013 LED ELEVATED HELIPORT LIGHT LHE INSTRUCTION MANUAL FOR USE INSTALLATION AND MAINTENANCE Figure 1 Exploded View...

Page 9: ...ug 1 11 Fixture grounding wire 1 Figure 2 Part List LHE I G D 25 C P 0 Basic P N Compliance I ICAO IEC S STANAG Colour W White G Green Y Yellow Mode D Parallel Circuits 48 V Height 00 w o pole 25 250...

Page 10: ...ting transformer is housed into a separate concrete pit which is normally placed close the above concrete block Figure 4 The pit can be placed far from the concrete block too but in this case a suitab...

Page 11: ...inch tube over the fixture cable assembly cable leads with plug plus yellow green wire and into the fixture body until the body bottoms against the tube approach without tighten the set screws on the...

Page 12: ...OFF DO NOT OPERATE ON LIVE PARTS LED lighting fixtures do not require frequent maintenance With well run installations and handling fixture carefully avoiding excessive falls or collisions the only ma...

Page 13: ...Operations Snowplow operators should exercise extra care not to strike the light fixtures with snowplow blades After snow removal operations inspect all light fixtures to locate and replace if necess...

Page 14: ...g ring Figure 6 Place a new gasket on the body Set the new lens on the body Hand tighten the locking ring Figure 6 Removing the Lens 4 5 LED MODULE REPLACEMENT Remove the lens with gasket as above des...

Page 15: ...ew electronic and reassembly the unit with reverse procedure IMPORTANT IT IS SUGGESTED TO REPLACE THE LENS GASKET TO NOT AFFECT WATERTIGHTNESS 4 7 BREAKABLE COUPLING REPLACEMENT Unscrew the lower thre...

Page 16: ...sert 4 8 2 Installing the new cable lead with plug Replace the cable gland if damaged Insert a new cable lead and a new grounding wire if necessary into the sealing insert at approx 8 cm from the free...

Page 17: ...TIVE Replace the Power PCB Moisture inside the fixture Execute leakage test and replace damaged components Clean and dry the inside area of the fixture No connection of primary circuit Check transform...