![NuAire MRXBOXAB-ECO5 Installation Manual Download Page 5](http://html1.mh-extra.com/html/nuaire/mrxboxab-eco5/mrxboxab-eco5_installation-manual_1715944005.webp)
5
28. 10. 21. Document Number 671956
Nuaire | Western Industrial Estate | Caerphilly | CF83 1NA | nuaire.co.uk
MRXBOXAB-ECO5
Installation Manual
Step 3:
The required airflow rates are as follows:
•
The maximum whole dwelling extract ventilation rate (e.g. boost)
should be at least the greater of step 1 and step 2. Note that the
maximum individual room extract rate should be at least those
given in
ADF 2010 - Extract Ventilation Rates table.
•
The minimum air supply rate should be at least the whole building
ventilation rate found in step 1.
For Scotland refer to BRE Digest 398.
For further information refer to “Domestic Ventilation Compliance
Guide” www.planningportal.gov.uk/buildingregulations/approved
documents/partl/compliance
3.8.1 Pre Commissioning MRXBOX MVHR Units
MRXBOX units are designed to ventilate the whole dwelling and must
not be used during site construction or the clean-up period. Cement
and plaster dust can be abrasive and can affect fan performance
and reliability. Please ensure that the filters are checked prior to
commissioning to ensure there is no build-up of dust or debris.
While the property is drying out, very high moisture levels are likely
to occur. Therefore it is advisable that if the installation and building
works are complete the unit is left running. If the building works are
not complete please close the air valves or cover up the air valves to
prevent condensation forming in the ductwork and the MRXBOX unit
due to natural migration of warm air.
3.9 Dimensions
658
623
432
Side View
Front View
Top View
4 x 150mm dia.
Spigots
458
16
120
226
226
Unit Weight = 25Kg
Mounting Bracket
(not to be used
when unit is fitted in
conjunction with
MRXBOX-AV5)
12
Unit Dimensions