Nuaire Group MRXBOX95B-LP1 Installation And Maintenance Manual Download Page 6

The filters fitted inside the unit are protected with a 

plastic film. Prior to commissioning remove the covers

(fig 13), take off the film and replace.

Isolation - Before commencing work make sure that 

the unit, switched live and Nuaire control are 

electrically isolated from the mains supply and 

switched live supply. 

6

24. 06. 13. Leaflet Number 671582

Installation and Maintenance

MRXBOX95B-LP1 Mechanical Ventilation with Heat Recovery & Summer Bypass

Figure 10. PCB inside enclosure.   

Access to second filter

Filter cover and 
filter being removed

Control module

Figure 11. Remove the two filter covers on the underside panel of the
unit, and the filters can be pulled out of the unit using the tab on
the lower edge of the filter. 

Technical or commercial considerations may, from time to time,

make it necessary to alter the design, performance and 

dimensions of equipment and the right is reserved to make such

changes without prior notice.

Control module

6.0 Commissioning

1. For the required air flow rates please refer to the design 

specification for the property, follow 2.4, or refer to building 

regulations ADF 2006/2010.

2. The unit is supplied with independent control for both normal 

and boost airflows. (see fig. 10). 

3. Correct commissioning is essential to ensure the ventilation 

air flowrates are met. It also ensures the unit is not over 

ventilating and causing excessive power consumption. 

4. Commissioning should be carried out in accordance with 

building regulations document “Domestic ventilation 

compliance guide”. A calibrated moving vane anemometer 

and hood will be required to carry out commissioning.

5. Adjustment valves should be locked in place to prevent 

further adjustment. 

6. Once commissioned the home owner / tenant should be 

informed that the unit should not be adjusted as it will have 

a detrimental effect on the indoor air quality and could result 

in condensation and mould growth. The label covering the 

control has an adhesive panel which should be removed post 

commissioning to prevent tampering.

7.0 Maintenance/Cleaning

We recommend that the two G3 fiters are inspected after 

6 months, and replaced every 12 to 18 months.

The filters can be removed from the unit by removing the two

filter covers on the bottom panel of the unit. Take hold of the

two circular tabs either end of the filter covers and pull to

remove. (see fig. 11). 

The filter can now be extracted by pulling the removal loop on

the edge of the filter. Once the filters have been inspected

return or replace them as necessary.

Inspect the heat exchanger every 5 years. Generally check 

for damage and security of components. Refit cover.

8.0 Replacement of Parts

Should any component need replacing Nuaire keep extensive

stocks for quick delivery. Ensure that the unit is electrically 

isolated, before carrying out any work.

Note: The supply cable must be replaced by an electrically 

competent person. 

When ordering spare parts, please quote the serial number 

of the unit and the ARC number of the purchase if possible.

(This information will be available on the fan label).

9.0 Warranty

The 5 year warranty starts from the day of delivery and

includes parts and labour for the first year and parts only for

the remaining 4 years. This warranty is conditional on planned

maintenance being undertaken

.

10.0 Service Enquiries

Nuaire can assist you in all aspects of service. Our service 

department will be happy to provide any assistance required, 

initially by telephone and If necessary arrange for an 

engineer to call.

Technical Support

029 2085 8400

Summary of Contents for MRXBOX95B-LP1

Page 1: ...the appropriate standards Ensure that the mains supply Voltage Frequency and Phase complies with the rating label Please note a clear working space is required around the installed unit to allow the c...

Page 2: ...uld be adjustable valve types not supplied External grilles to have a minimum free area of 12 250 sq mm 2 3 Ducting Before commencing ducting installation reference should be made to building regulati...

Page 3: ...the whole dwelling ventilation supply rate from Table 2 0 04 x gross internal volume of the dwelling heated space m3 Step 2 Calculate the whole dwelling extract ventilation rate by summing the individ...

Page 4: ...n ceilings Exhaust air from kitchen bathroom to outside via air brick Part no PVC505NS Supply and extract ducts from external air bricks to the unit needs to be insulated Minimum 300mm Top of ceiling...

Page 5: ...rey Green yellow Unit serving kitchen and bathroom Unit serving kitchen and two bathrooms Figure 8 Figure 9 For good EMC engineering practice any sensor cables or switched live cables should not be pl...

Page 6: ...nt further adjustment 6 Once commissioned the home owner tenant should be informed that the unit should not be adjusted as it will have a detrimental effect on the indoor air quality and could result...

Page 7: ...nge speed This is normal and will have no adverse effect on the fan The speed will return to normal once the interference has subsided 5 0 INSTALLATION REQUIREMENTS In addition to the particular requi...

Page 8: ...ings assessed under The Building Regulations 2010 specifically SAP 2009 and Approved Documents L and F Completion of this document is therefore only required for dwellings assessed by SAP 2005 Custome...

Page 9: ...r to overcome particular obstructions If flexible ducting has been used has it been pulled taut to minimise system resistance Has the number of duct bends been minimised to ensure adequate air flow an...

Page 10: ...y unit been fixed to a stable element of the building fabric e g wall or floor using manufacturer recommended supplied fixing brackets Has the condensation drain been fitted and the pipe insulated Hav...

Page 11: ...or N A Has the rating label been verified to establish suitability for the installation strategy and whether an earth is required e g voltage class I or II product status Has a local isolator been pro...

Page 12: ...tion grilles been locked where possible to minimise unapproved occupant adjustment Figure 3 Ensure all external and internal windows and doors are closed Set fan speed using manufacturer data table Se...

Page 13: ...e customer been advised that opening windows is not recommended during normal use in order to ensure the energy efficient operation and performance of the balanced system Has the customer been advised...