Chapter 37 Hardware procedures 417
Passport 7400 Hardware Installation, Maintenance, and Upgrade 5.2S1
Unpacking a 5-slot Passport switch
Unpack a 5-slot Passport switch close to the installation site.
Procedure steps
1
Set the box on floor with top end down.
2
Cut tape sealing the bottom flaps.
3
Fold back the bottom flaps against the outside sides of the box.
4
Turn the box right side up as you hold the bottom flaps out.
5
Lift the box up and off of the switch.
6
Remove the box that contains the power supply.
7
Remove the packing material.
8
Compare the contents of your shipment with the table “Equipment
checklist for unpacking a 5-slot Passport switch” (page 417)and the figure
“Taking inventory after unpacking a 5-slot Passport switch” (page 419) to
ensure you have all the hardware components you require.
Table 11
Equipment checklist for unpacking a 5-slot Passport switch
Equipment
Switch with pre-installed:
•
Function processors (1 to 4 for each switch)
•
Blank processor cards (4 for each switch less the number
of function processors)
•
Fan tray and filter assembly
Power supply and a blank power supply
Ac power cords (1 for each power supply)
or
Dc power wiring. See 241-7401-200
Passport 7400
Hardware Description for dc power cabling requirements.
Control processor (1 or 2)
Function processor cables
(Sheet 1 of 2)
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......