250 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Installing a rack-mounted alarm panel
Install a rack-mounted alarm panel so that you can monitor the status of a 16-
slot Passport switch if your switch is not installed in a cabinet.
Prerequisites
•
You will need an alarm panel assembly with PEC NTJS74.
Procedure steps
1
Install the alarm panel. Follow the procedure “Installing a 19” rack-
mounted termination panel” (page 205).
2
Connect the alarm panel cable to the alarm cable connector on the alarm
panel. See the figure “Rack-mounted alarm panel” (page 250).
Figure 87
Rack-mounted alarm panel
3
Route the cable down to the shelf assembly and connect it to the door
alarm connector on the back of the shelf. See the figure “Dual alarm shelf
interconnection” (page 377).
PPT 2497 001 AA
Power LED
Alarm cutoff
Minor alarm LED
Major alarm LED
•
•
•
•
•
•
•
•
Alarm cable
connector
•
•
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......