Reznor, Guardian 1 Phase Electric Heat, Installation Manual, EN 2021-08, D301299 Iss D Page No 13
I
Installation process
1. Remove all packaging and covers
Note All outer metal surfaces are covered
by a protective plastic film, which must be
removed before final fixing and operation
of the unit.
2. GS units, Loosen (DO NOT REMOVE) the
screws in the top of each front inlet cover
[1] (see figure 9.1and 10 dog bone slot)
then slide the left cover to the left [2]
which will allow the cover to slide under
the end cap. This will allow the next cover
to be pushed to the left [3] (see figure
9.1) allowing it to be released from the
screw slot [4] by pulling forward and lifted
upwards out of the lower grove in the
case.
3. The first cover can then be pushed to the
right to release it from the screw slot,
(see figure 10) then pull forward and lift
upwards to be removed. For additional
covers fitted on the 1500 or 2000 units
loosen the fixing screws and remove as
with the previous covers.
Figure 9 GS cover fixing point
Figure 9.1 GS cover fixing point
Figure 9.2 GS cover fixing point
Figure 10 Dog bone screw fixing slot
4. On the GS units the lower cover can be
removed by removing the two screws at
the top of this cover and then pulled out of
the tabs from the main case
Figure 11 GS lower access panel
1. The GR has two captive screws in each
panel, loosen these and hinge the panel
down.
2. The panel can be removed completely by
releasing the bolt hinges on either side of
the panel (see figure 13).
Figure 12 GR cover fixing point
Figure 13 GR bolt hinge
1
1
1
1
2
3
4
4
Summary of Contents for 1000E-1PH
Page 2: ......