Allow only qualified personnel

to perform the following tasks.  Follow the

safety instructions in this document and all

other related documentation.

See Figure 1.

Severe personal injury could result if hands

or fingers are caught between the follower

plate (10) and container (11).  Keep hands

clear of this area.

Do not open the bleed valve (not shown)

more than three turns.  The bleed valve

and material may be forced from the valve

body.

NOTE:  

Refer to the unloader controls manual

for detailed operation information.

Daily Operation

The following paragraphs provide daily operation

procedures.

Startup

1. Make sure that the air pressure to the system is

shut off.

2. Perform the following:

S

Check the unloader to determine if material
is leaking past the follower plate (10).  If a

follower plate seal is damaged, refer to the

Rhino VE Follower Plate Module 

manual for

repair procedures.

S

Check the amount of material in the

container (11).  Replace the container if

necessary.  Refer to the following 

How to

Change the Container 

procedure.

S

Check the solvent chamber fluid levels and
fill if necessary.

3. Turn on the input air supply to the unloader.

4. Place the ram control valve (2) in the

 Down

position.

5. If required, adjust the air motor regulator to the

desired air supply pressure.

Temporary Shutdown

1. Turn off the input air supply to the unloader.
2. Place the ram control valve (2) in the 

Neutral

position.

Restart After Temporary

Shutdown

1. Turn on the input air supply to the unloader.
2. Place the ram control valve (2) in the 

Down

position.

How to Change a

Container

See Figure 1.

The unloader may have options that the previous

unloader did not have.  These procedures include

steps for the blow-off option.  For additional

assistance, contact Nordson customer support.

1. Set the air motor lockout valve (1) to 

Off

.

2. Place the ram control valve (2) in the 

Neutral

position..

3. Remove the bleeder stem (8) and replace with

the blow-off tube (5).

4. Connect the hose (7) to the blow-off tube (5).
5. Place the ram control valve (2) in the 

Up

position.  If the container (11) begins to rise off

the unloader frame, the ram-up speed can be

adjusted to match the follower plate ascent rate.
a. Make sure the blow-off tube (5) and follower

plate (10) are not obstructed with material.

b. Place the ram control valve (2) in the 

Down

position until the container (11) comes to

rest on the base, then place the ram control

valve in the 

Neutral

 position.

c. Locate the exhaust flow control valve (3) on

the side of the ram control valve (2).

Increase the flow restriction by loosening

the jam nut, turning the center screw a few

turns at a time (clockwise), and

re-tightening the jam nut or press the

blow-off circuit button (4).