Venting the system
NOTE
Hot fluids and hot vapour may occur.
Fluid with air
1
Flow direction
2
Aerated fluid
3
Venting valve
4
Blowhole
5
Air/fluid
6
1.
Route the blowhole (5) to the collector.
2.
Open the venting valve°(4).
The separated air is drained from the vessel.
3.
Close the valve as soon as fluid comes out of the
pipe.
Operation and maintenance
For safety reasons the fluid must be able to run out of
the safety valve during the heating process.
႑
Do not close
the safety valve.
႑
Check the unit before restarting it when the safety
valve has been deployed (normally only occurs at start
up).
Problem free operation is only possible with open ball
valves (position 0°. See section Start-up and inspection
on page 14.
Maintenance intervals
Activity
When
Drain, flush and fill the sy-
stem.
Flow meter can no longer
be read off.
Replace the circulation
pump.
Fault in the circulation
pump.
15
GB
Summary of Contents for SPS 10
Page 2: ......
Page 9: ...Tekniska uppgifter M tt 220 80 410 314 154 240 100 70 9 SE...
Page 11: ...Pumpdiagram 11 SE...
Page 18: ...Technical data Dimensions 220 80 410 314 154 240 100 70 18 GB...
Page 20: ...Pump diagram 20 GB...
Page 27: ...Technische Daten Ma e 220 80 410 314 154 240 100 70 27 DE...
Page 29: ...Pumpendiagramm 29 DE...
Page 36: ...Tekniske oplysninger Dimensioner 220 80 410 314 154 240 100 70 36 DK...
Page 38: ...Pumpediagram 38 DK...
Page 45: ...Tekniset tiedot Mitat 220 80 410 314 154 240 100 70 45 FI...
Page 47: ...Pumppuk yr 47 FI...
Page 48: ...48 FI...
Page 49: ...49 FI...
Page 50: ...50 FI...
Page 51: ......