HYDRAULIC - PNEUMATIC - ELECTRICAL - ELECTRONIC SYSTEMS - ELECTRICAL POWER SYSTEM
Installing stop solenoid (ETR type)
93101328
3
Procedure for installing stop solenoid (ETR type)
1.
Apply Threebond 1212 or 1211 sealant to the
threaded portion
(1)
of the stop solenoid
(2)
.
NOTE:
Apply the sealant up to the position where the stop
solenoid is screwed into the governor case.
2.
Temporarily reassemble the stop solenoid and the
nut
(3)
to the governor case.
3.
Move the control rack of the fuel injection pump fully
in the stop direction.
4.
Screw in the stop solenoid until the shaft contacts the
tie rod.
5.
Turn the stop solenoid in the reverse direction by
30 to 45° from the above condition and temporarily
tighten the nut.
6.
Move the control rack side to side and make sure
that there is play of approximately
0.15 - 0.20 mm
(
0.0059 - 0.0079 in
).
7.
Tighten the nut to the specified torque.
Verification after reassembling (ETR type)
1.
After starting the engine, turn the starter switch key
to the OFF position, and make sure that the stop
solenoid activates and the engine stops.
2.
After starting the engine, make a short circuit be-
tween the terminal of the oil pressure switch and the
switch body, and make sure that the engine stops.
84373329 09/08/2010
A.30.A / 10