Commissioning Cycle

Function test

Self-test

A tri-colour LED indicator displays the light fitting status. The indication colours are 

shown in table 1.

a. Commissioning Cycle

Starts automatically after 24 hours of uninterrupted charging.

3 charge/discharge cycles to optimise battery’s full capacity.

Battery is charged for 24 hours before each discharge cycle.

No need for manual commissioning

b. Function Test

Carried out every 7 days.

Checks the function of the battery, lamp and power supply.

Lasts for few minutes only.

RB Intelligent Emergency Operation Guide

Operation

The light fitting will carry out the following function 

automatically

 after installation:

7.

The  battery  fuse  located  within  the  Bulkhead  housing  on  emergency  variants  is 

disconnected  after  final  manufacturing  testing.  When  installing  the  bulkhead 

the battery fuse will need to be reconnected and the unit charged for 24 hours and 

then discharged (repeated 3 times) to bring the battery up to peak capacity. 

(Unless an ‘EMX’ intelligent emergency variant – see notes below)

8.

If a 4 core cable is used on emergency luminaires – L1, L2, N and E the link cable at 

the front of the terminal block between L1 and L2 should be removed

9.

During emergency operation the light output and duration will be determined by 

the variant purchased

10.

If carrying out Insulation Resistance tests the normal method of insulation 

testing is to connect Live and Neutral together and test between this point 

and Earth to prevent the risk of damage to the electronic control gear. 

5

-

1

2

www.nemalux.com  |   [email protected]  |   Tel 403•242•7475  |   Fax 403•243•6190 

SUBJECT TO CHANGE WITHOUT NOTICE

MADE IN 

UK

Summary of Contents for RB Series

Page 1: ...n 5 Declaration of Conformity Important information The RB series of explosion protected bulkheads are specialist devices certified for use in specific operating environments The units must be install...

Page 2: ...TEX IEC Ex UKEX cable glands and stopper plugs these must be parallel thread have a minimum of 5 full thread engagement and be of a medium fine tolerance to ISO965 1 and ISO965 3 The cable entry devic...

Page 3: ...sed the fixing points must be suitable for the conditions of use Nemalux recommends using M6 Marine Grade A4 Stainless Steel fixings not supplied 121 104 302 288 204 220 182 240 220 168 70 20 17 3 3 1...

Page 4: ...cable into the terminal block Provision has been made for this and identified as the E Earth L1 Live switched L2 Live permanent and N Neutral terminals There are two pairs of contacts for each of thes...

Page 5: ...emergency variants is disconnected after final manufacturing testing When installing the bulkhead the battery fuse will need to be reconnected and the unit charged for 24 hours and then discharged rep...

Page 6: ...t the same time LED indication c Self test Carried out at a random time every 3 month Checks the battery s capacity and lamp s condition Performs self recovery for the battery if not at peak capacity...

Page 7: ...mbly clear Re fitting a light engine is a reversal of the above procedure 5 The unit has one independent power supply in the event that the power supply needs to be replaced the cables to the LED and...

Page 8: ...ncy 50 60Hz Inrush Current Ipeak 50 20A t 300 s Total Harmonic Distortion 230Vac full load 10 IP Rating IP66 67 Weight std 5Kg 6Kg Dimensions See previous pages for line diagrams ATEX and IECEx and UK...

Page 9: ...30V MCB Type Rating RB 2 STD RB 2 EM B 10A 11 10 B 16A 17 15 B 20A 25 22 B 25A 35 32 C 10A 24 20 C 16A 34 28 C 20A 49 44 C 25A 58 55 9 12 www nemalux com sales nemalux com Tel 403 242 7475 Fax 403 243...

Page 10: ...sole responsibility that the product s listed below conform with the relevant provisions of the ATEX directive 2014 34 EU of 20th April 2016 and the UK directive SI 2016 No 1107 as amended Manufacture...

Page 11: ...014 11 12 www nemalux com sales nemalux com Tel 403 242 7475 Fax 403 243 6190 SUBJECT TO CHANGE WITHOUT NOTICE MADE IN UK And also 2014 35 EU Low Voltage Directive 2014 30 EU EMC Directive Signed Name...

Page 12: ...2589 P 1 403 242 7475 F F 1 403 243 6190 E info nemalux com W www nemalux com Industrial LED Lighting designed to solve harsh and hazardous lighting challenges 12 12 www nemalux com sales nemalux com...

Reviews: