Neles PB2 Series Installation Maintenance And Operating Instructions Download Page 4

1PB270EN - 10/2020

4

2.  TRANSPORTATION AND 

STORAGE 

Check the valve and the accompanying devices for any damage 

that may have occurred during transport. 

Store the valve carefully. Store indoors in a cool, dry place. 

Do not remove the flow port protectors until installing the valve.

Move the valve to its intended location just before installation.

If the valve(s) are to be stored for a long duration, follow the 

recommendations of IMO-S1. 

3.  INSTALLATION 

3.1 GENERAL 

Remove the flow port protectors and check that the valve is clean 

inside. Clean valve if necessary.
Flush the pipeline carefully before installing the valve. Foreign 

objects, such as sand or pieces of welding electrodes, will damage 

the ball and seats.

3.2 INSTALLING IN THE PIPELINE 

WARNING: 

THE VALVE SHOULD BE TIGHTENED BETWEEN 

FLANGES USING GASKETS AND FASTENERS 

COMPATIBLE WITH THE APPLICATION, AND IN 

COMPLIANCE WITH APPLICABLE PIPING CODES 

AND STANDARDS. CENTER THE VALVE AND FLANGE 

GASKETS CAREFULLY BETWEEN FLANGES. DO NOT 

ATTEMPT TO CORRECT PIPELINE MISALIGNMENT BY 

MEANS OF FLANGE BOLTING!

The valve may be installed in any position and offers tight 

shut-off in either flow direction. When in a horizontal line, it is not 

recommended to install a valve with the stem on the underneath 

side as debris in the pipeline may enter the body cavity and damage 

the gland packing.
Refer to Section 4, MAINTENANCE for gland packing adjustment. If 

there is seepage past the gland packing upon installation, it means 

the valve may have been subject to wide temperature variations in 

shipment. Leak-tight performance will be restored by a simple stem 

seal adjustment described in the MAINTENANCE section.

3.3 VALVE INSULATION

Neles™ ball valves do not require insulation. If desired, the valve 

may be insulated; however, the insulation must not continue above 

the upper level of the valve. See 

Figure 2.

Figure 2. 

Insulation of the valve

3.4 ACTUATOR

WARNING: 

WHEN INSTALLING THE ACTUATOR ON THE 

VALVE, MAKE SURE THAT THE VALVE ASSEMBLY 

FUNCTIONS PROPERLY. INFORMATION ON ACTUATOR 

INSTALLATION IS GIVEN IN SECTION 7 OR IN THE 

SEPARATE ACTUATOR INSTRUCTIONS.

The actuator should be installed in a manner that allows plenty of 

room for its removal.

The actuator must not touch the pipeline, tanks, walls, or other 

equipment because vibration may interfere with its operation.

3.5 COMMISSIONING

Ensure that there is no dirt or foreign objects left inside the valve 

or pipeline. Flush the pipeline carefully. Make sure that the valve is 

fully open when flushing.
Ensure that all nuts, fittings, and cables are properly fastened.
If so equipped, check that the actuator positioner and/ or switch(s) 

are correctly adjusted. Actuator adjustment is in Section 5. To 

adjust any accompanying device(s) refer to the separate control 

equipment instruction manuals.

4.  MAINTENANCE 

4.1 GENERAL 

Although Neles™ valves are designed to work under severe 

conditions, proper preventative maintenance can significantly help to 

prevent unplanned downtime and reduce the total cost of ownership. 

Summary of Contents for PB2 Series

Page 1: ...Neles PB2 series full bore flange PFA lined ball valve NPS 1 2 6 Installation maintenance and operating instructions 1PB270EN 10 2020...

Page 2: ...ck cover Table of contents GENERAL 3 Scope of the Manual 3 Valve markings 3 Safety Precautions 3 Technical Specification 3 TRANSPORTATION AND STORAGE 4 INSTALLATION 4 General 4 Installing in the Pipel...

Page 3: ...ERIALS HAVE PRESSURE RATINGS THAT ARE LESS THAN THE BODY RATING ALL OF THE BODY AND SEAT RATINGS ARE DEPENDENT ON VALVE TYPE AND SEAT MATERIAL DO NOT EXCEED THESE RATINGS WARNING BEWARE OF BALL MOVEME...

Page 4: ...there is seepage past the gland packing upon installation it means the valve may have been subject to wide temperature variations in shipment Leak tight performance will be restored by a simple stem s...

Page 5: ...s 3 Lift the actuator straight up in line with the valve stem until the connection between actuator drive and valve stem is completely disengaged 4 Place actuator in a safe location to avoid damage or...

Page 6: ...ball onto the stem 4 and against the seat 5 Make certain the stem is roughly in the middle of the ball slot 13 Place the second seat 5 into the cap 2 in the correct orientation so the proper surface...

Page 7: ...nted the valve position should correspond to the indicated actuator position 2 Assemble actuator onto the valve ensuring full engagement between the stem and actuator drive and the actuator fully cont...

Page 8: ...Ball ASTM A351 CF8 PFA or ASTM A276 304 PFA 4 Stem ASTM A276 304 PFA 5 Seat TFM 1600 6 Gland ASTM A351 CF8 7 Gland packing PTFE 8 Handle ASTM A216 WCB ASTM A351 CF8 9 Stop plate ASTM A276 304 10 Washe...

Page 9: ...ody Ball Stem S4 CF8 PFA 304 PFA 304 PFA D2 DI PFA 304 PFA 304 PFA 6 sign Material of seat Z TFM 1600 7 sign Packing material T PTFE Live loaded packing 8 sign Version A Model A NOTE As the use of the...

Page 10: ...1PB270EN 10 2020 10...

Page 11: ...11 1PB270EN 10 2020...

Page 12: ...151 neles com Subject to change without prior notice Neles Jamesbury and Easyflow by Neles and certain other trademarks are either registered trademarks or trademarks of Neles Corporation or its subsi...

Reviews: