Issue 2.0
3-4
Installing the SV9100 Chassis
The system requires a dedicated 100 - 240 VAC 50/60 Hz circuit located within
seven feet of the AC receptacle. Telco should install the RJ21X to the right of the
Controlling Chassis. Extension blocks should be installed to the left of the
Controlling Chassis.
Chassis are shipped fully assembled. The following are included with the chassis:
19” Chassis (CHS2UG)
One black 3-prong power cord (packed outside the chassis)
CHS2UG RACK MOUNT KIT
9.5” Gateway Chassis (CHS2UG GW)
One black 3-prong power cord (packed outside the chassis)
Wall Mount Kit
Stand Mount Kit
9.5” Base and Expansion Chassis (CHS2UG B and CHS2UG E)
One black 3-prong power cord (packed outside the chassis)
Wall Mount Kit
Stand Mount Kit
2.5 Power Failure Transfer
The Power Failure Transfer relays are located on the COIU blades (CN3). When
selecting a Single Line Telephone for power failure transfer, make sure it matches
the CO line dialing type (10 pps, 20 pps, or DTMF) where it is connected. Each
COIU blade supports two power failure transfer connections. During a power
failure condition, CO Ports 1 and 2 on the COIU Blade are used for Power Failure
Transfer relays 1 and 2 consecutively.
Table 3-1 Power Failure Transfer
is a relay diagram. The relay is shown with the power ON.
NOTE
Power Failure and FAX Branch Connection do not function
simultaneously on the same port. Use Program 14-02-21 (Fax Branch
Connection) to enable this feature per trunk.
Table 3-1 Power Failure Transfer Connections
Pin Number
Description
Pin Number
Description
1
Not in Use
2
Not in Use
3
Tip for Circuit 2
4
Ring for Circuit 1
5
Tip for Circuit 1
6
Ring for Circuit 2
7
Not in Use
8
Not in Use
Summary of Contents for Univerge SV9100
Page 1: ...System Hardware Manual A50 035028 001 GE ISSUE 2 0 SV9100...
Page 22: ...xviii Table of Contents Issue 2 0...
Page 42: ...xxxviii List of Tables Issue 2 0...
Page 72: ...Issue 2 0 1 18 Introduction to SV9100...
Page 76: ...Issue 2 0 2 4 SV9100 System Specifications Figure 2 1 SV9100 System Block Diagram...
Page 186: ...Issue 2 0 3 64 Installing the SV9100 Chassis Figure 3 78 Brackets Small Batt Box...
Page 238: ...Issue 2 0 3 116 Installing the SV9100 Chassis...
Page 269: ...Issue 2 0 SV9100 System Hardware Manual 4 31 Figure 4 12 VoIP Connections...
Page 317: ...Issue 2 0 SV9100 System Hardware Manual 4 79 Figure 4 29 Control Signal Connection...
Page 342: ...Issue 2 0 4 104 Installing the SV9100 Blades...
Page 476: ...Issue 2 0 6 26 Installing SV9100 Cordless Telephones...
Page 482: ...Issue 2 0 7 6 Installing SV9100 Optional Equipment Figure 7 5 PGDAD Connection Diagram...
Page 489: ...Issue 2 0 SV9100 System Hardware Manual 7 13 Figure 7 12 Installing a Door Box...
Page 499: ...Issue 2 0 SV9100 System Hardware Manual 7 23 Figure 7 17 PGDAD Connections...
Page 556: ...System Hardware Manual NEC Corporation Issue 2 0 SV9100...