Reboot/Power Down for Single Cabinet System
In the event of a reboot or complete power down, if you only have a single cabinet, please
follow the instructions below.
1.
Press both of the power switches to the off position
2.
The system will power down, leave the system powered off if required (Due to electrical
work being carried out)
3.
Alternatively, count to 10 and then press both of the power switches to the on position
4.
The system should be up and operational within 5 minutes.
Reboot/Power Down for 2 Cabinet System
In the event of a reboot or complete power down, if you have 2 cabinets, please follow the
instructions below.
1.
On the top cabinet press both of the power switches to the off position
2.
On the bottom cabinet, press both of the power switches to the off position
3.
The system will power down, leave the system powered off if required (Due to electrical
work being carried out)
4.
Alternatively, count to 10 and then press both of the power switches to the on position
on the top cabinet
5.
Press both of the power switches to the on position on the bottom cabinet
6.
The system should be up and operational within 5 minutes.
Reboot/Power Down for 3 Cabinet System
In the event of a reboot or complete power down, if you have 3 cabinets, please follow the
instructions below.
1.
On the top cabinet press both of the power switches to the off position
2.
On the middle cabinet, press both of the power switches to the off position
3.
On the bottom cabinet, press both of the power switches to the off position
4.
The system will power down, leave the system powered off if required (Due to electrical
work being carried out)
5.
Alternatively, count to 10 and then press both of the power switches to the on position
on the top cabinet
6.
Press both of the power switches to the on position on the middle cabinet
7.
Press both of the power switches to the on position on the bottom cabinet
8.
The system should be up and operational within 5 minutes.