It is the installer’s responsibility to ensure the installation is done as
per the installation method provided.
This document must be completed when installing any HVC Fire
Damper.
By signing this document you are declaring that the correct
installation method has been followed.
Check:
Yes/No
Is the installed damper the correct type?
Is the damper installed correctly?
Has the damper been correctly identified?
Has the correct orientation been used?
Are there sufficient access routes installed?
Has a check of the damper been carried out for:
Internal cleanliness?
Damage?
Obstructing debris?
Has a drop test been carried out?
At the time of handover is the fire barrier and penetration seal complete?
I hereby confirm that the damper detailed above has been
installed in accordance with HVC Supplies (Stourbridge) Ltd’s
tested installation method, and has been tested as above.
Damper unique system I.D. (If applicable):
Damper location:
Installation address:
Damper type:
e.g. S100BGP
Link rated temperature:
Notes:
Installer’s name:
Company name:
Company address:
Company telephone number:
Installation guide: Series 100 fire damper c/w plate frame
Approved installation method, operation and installation declaration
Page 2 of 2 - Issue D - 26/02/2018
Installation Declaration for Series 100 Fire Dampers
Installer’s signature: