Installation of the Boiler.
General Guidelines:
1.
The boiler should only be installed by qualified installers with
"Certificate for installation and service of small biofuel plant“
and must be installed according to AT guidance on technical equipment - B.4.8
(Applicable in DK)
2.
The boiler must
not
be installed on combustible surfaces.
3.
Un-insulated smoke pipe must
not
exceed 0.30 m long,
and must be provided with an access door.
4.
Chimney draft should be a
min.
5 PA. and be stable.
Overpressure must
not
occur. It is always recommended
Draft stabilizer
to install a draft stabilizer.
5.
The boiler must be installed with an approved
mixing valve, and the return must be at min. 55 degrees C,
otherwise there can not be sustained guarantee on
the boiler.
Approved mixing valve