  DANGER 

 

When conversion is required, be sure to set the Front Panel  DIP 
switches according to the supply gas type. 

 

Failure to properly set the DIP switches could cause carbon monoxide 
poisoning, resulting in severe personal injury or death. 

 

11.  Measure and adjust the gas/air ratio. 

Option 1. Using Combustion Analyzer (recommended) 
a.  Loosen the screw, rotate the plate and remove the gasket   

to access the emissions monitoring port as shown in Figure 7. 

b.  Insert the analyzer into the port (Figure 7). 

Figure 7 

 

Table 2. CO

2

 value 

(CO

2

 values must be within 0.5% of the values listed.) 

 

c.  Fully open several hot water fixtures and set the water 

heater to operate at 1-stage MIN mode (refer to page 8). 

Measure the CO

2

 value at low fire. 

If the CO

2

 value is not within 0.5% of the value listed in 

Table 2, the gas valve set screw will need to be adjusted. 
If adjustment is necessary, locate the set screw as shown 
in Figure 8. Using a 5/32”or 4mm Allen wrench, turn the 

set screw no more than 1/4 turn clockwise to raise or 

counterclockwise to lower the CO

2

 value. 

Water 

Heater 

Fuel 

High fire 

Low fire 

%CO

2

 

%CO

2

 

NPE-180A 

NPE-180S 

NG 

8.9 

9.5 

LP 

10.2 

10.8 

NPE-210A 

NPE-210S 

NG 

8.9 

9.5 

LP 

10.2 

10.8 

NPE-240A 

NPE-240S 

NG 

8.9 

9.5 

LP 

10.2 

10.8 

b.

 

Connect a manometer to the offset pressure port. For 
dual port manometers, use the positive pressure side. 

 

Model 

Kit Part No. 

Gas Type 

Offset 

NPE-180A 

NPE-180S 

NAC-01 

LP 

-0.03"±0.01" 

NAC-100 

NG 

-0.04"±0.01" 

NPE-210A 

NPE-210S 

NAC-02 

LP 

-0.02"±0.01" 

NAC-200 

NG 

-0.04"±0.01" 

NPE-240A 

NPE-240S 

NAC-03 

LP 

-0.02"±0.01" 

NAC-300 

NG 

-0.04"±0.01" 

Table 3. Offset value for low fire 

 

c.

 

Fully open a hot water fixture and set the water heater 
to operate at 1-stage MIN mode (refer to page 8). 

Measure the offset value at low fire and compare it to 

the values in Table 3. If the offset value is out of range, 

the gas valve set screw will need to be adjusted. 

If adjustment is necessary, locate the set screw as 

shown in Figure 10. Using a 5/32”or 4mm Allen wrench, 
turn the set screw no more than 1/4 turn clockwise to 

raise or counterclockwise to lower the offset value. 

 

Figure 10 

  The set screw is located behind the screw-on cover. 

This must be removed first. 

d.

 

At high fire, do not check the offset value and never adjust the 

gas valve. 

 

  DANGER 

Improper gas valve settings can cause severe personal injury, death or 
substantial property damage. 

 

 

Figure 8. Set Screw Location 

 

 

The set screw is located behind the screw-on  cover. 
This must be removed first. 

d.  Fully open several hot water fixtures and set the water heater to 

operate at 2-stage MAX mode (refer to page 8). Measure the CO

2

   

value at high fire. 

If the CO

2

 values do not match Table 2 at high fire, do not adjust the 

gas valve. Check for the proper Gas Orifice. 

 

  DANGER 

Improper gas valve settings can cause severe personal injury, death or substantial 
property damage. 

 

Option 2. Using Digital Manometer 

a.

 

Open the offset pressure port by loosening the screw 

two turns as shown in Figure 9. 

 

Figure 9 

 

12.

 

  Once the CO

2

 or offset values have been confirmed, apply 

the included conversion stickers to show that the appliance 

has been converted to propane gas. Place these labels 

adjacent to the rating plate as shown in Figure 11. 

 

Figure 11. Proper Placement of Gas Conversion Labels 

  Manifold Gas Pressure ratings can change due to 

updated orifice sizes. Please confirm new 

manifold pressures approved by CSA before 

production of gas conversion labels. 

 

 

Setting the Operation Mode 

1.

 

Using the Front Panel, press and hold the Diagnostics Button for 

over 5 seconds until “1.TST” is displayed. 

2.

 

Press the + (Up) button once to change the display to“2.OPR”. 

3.

 

Press the Information Button once to access the Operation Mode 

menu. 

4.

 

Press the + (Up) button once to set the water heater to operate at 1-

stage MIN (“MIN.1”). 

5.

 

To set the water heater to operate at 2-stage MAX, press the (Up) 

button 3 times or until“MAX.2” is displayed. 

6.

 

To exit the Operation Mode and return the water heater to normal 

operation, press the Reset button twice. 

 

 

Diagnostics 

Information 

Reset 

Navien America, Inc. 
20 Goodyear lrvine, CA 92618 
TEL +949-420-0420 FAX +949-420-0430 
www.navienamerica.com

 

Reviews: