XR6/XR3 Pre-installation Manual
Pre-installation tasks
Issue 3.0 2009-07-15
Page 2-1
Section 2:
Pre-installation tasks
This section provides a list of tasks that you must perform prior to delivery and installation of the
XR6/XR3 transmitter.
Preparing for installation
To prepare for installation of an XR6/XR3 transmitter, perform the following tasks:
1. Ensure that the correct transmitter configuration is ordered. Check the ac power
requirements, preset frequency, IBOC option, and other options.
2. Select a location for the transmitter in the transmitter room. Determine whether additional
heating, ventilating or cooling capacity is needed at the site. Identify any special requirements
regarding air flow around the cabinet (for example, ducting hot air away from the cabinet, or
bringing in external cooling air).
3. If this is an upgrade or replacement transmitter (that is, if the site is already set up for a
transmitter), go to
. (If you are upgrading a site, verify the feedline, the lightning
protection systems, and the ac power service. Refer to the
Nautel Site Protection Manual.
)
4. Install ac power service into the planned location of the transmitter, and select a location for
an ac power disconnect near the transmitter location. For detailed information, see
“Electrical power” on page 5-1
.
Be aware of lightning protection issues when installing ac power. Lightning protection is
essential to protect both personnel and equipment at your site. Refer to the
Nautel Site
Protection Manual.
5. Install lightning protection on the antenna tower. Refer to the
Nautel Site Protection Manual.
6. Place a work area with a clear table surface near the transmitter location. Provide electrostatic
protection measures in the work area.
7. Order any accessories or optional equipment that you may need.
WARNING: FAILURE TO COMPLY WITH RECOMMENDATIONS MAY VOID
YOUR MANUFACTURER’S WARRANTY. FOR MORE INFORMATION, REVIEW
YOUR WARRANTY DOCUMENTS.
Summary of Contents for XR6
Page 2: ...blank...
Page 4: ...blank...
Page 8: ...XR6 XR3 Pre installation Manual Page viii Issue 3 0 2009 07 15...
Page 12: ...XR6 XR3 Pre installation Manual Page xii Issue 3 0 2009 07 15...
Page 20: ...XR6 XR3 Pre installation Manual Page xx Issue 3 0 2009 07 15...
Page 24: ...XR6 XR3 Pre installation Manual Description Page 1 4 Issue 3 0 2009 07 15...
Page 28: ...XR6 XR3 Pre installation Manual Pre installation tasks Page 2 4 Issue 3 0 2009 07 15...
Page 34: ...XR6 XR3 Pre installation Manual Physical requirements Page 3 6 Issue 3 0 2009 07 15...
Page 38: ...XR6 XR3 Pre installation Manual Cooling requirements Page 4 4 Issue 3 0 2009 07 15...
Page 56: ...XR6 XR3 Pre installation Manual Control and monitoring Page 6 14 Issue 3 0 2009 07 15...
Page 62: ...XR6 XR3 Pre installation Manual RF output requirements Page 8 4 Issue 3 0 2009 07 15...
Page 66: ...XR6 XR3 Pre installation Manual Parts and tools Page 9 4 Issue 3 0 2009 07 15...
Page 88: ...XR6 XR3 Pre installation Manual Page IX 6 Issue 3 0 2009 07 15...
Page 89: ......