RM-26999 Calibration Procedure
22
ni.com/calibration
22.
Call
RM-26999 Adjust AC Calibration.vi
.
a.
Use the high voltage value as the adjustment signal, as defined in
b.
Use the low voltage value as the measured voltage signal, as
defined in Table 5.
23.
Call
RM-26999 Close External Calibration.vi
with the
commit
action to store all scaling coefficients for both DC and AC on the DUT EEPROM.
Perform Reverification
Perform all tests in the Verification section after completing Adjustment. This
verification compares the As-Left limits with measurement data collected after the
DUT adjustment. The As-Left limits may be tighter than the As-Found limits.
Revision History
Revision
Section
Changes
377699A-01
December 2020
—
This is the initial release version of the RM-26999 Calibration
Procedure.