9.   Install valve at tapped coupling.

Notes:

1.  The Certa-Set main line piping and couplings can be disassembled and reused. See Main Line 

Disassembly.

2.  Tapped couplings can be easily stripped if threads are not aligned properly. Take precautionary steps to 

prevent cross threading.

Best Practices:

Turn the pipe backward so the female end drops in, then tighten.  This eliminates stripped threads.

Tapped coupling

Threaded adapter

Nelson valve

Tapped coupling 

assembly

Nelson valve installed onto 

tapped coupling

Secure Nelson valve 

installed onto tapped 

coupling with spline

Nelson valve

Summary of Contents for Certa-Set

Page 1: ...Certa Set Field Installation Guide ...

Page 2: ...itional installation information please visit napcopipe com Lubricant Applying lubricant Properly installed O ring Applying lubricant Lubricant Notes 1 Avoid getting lubricant in the spline grooves 2 Do not use excess lubricant O ring missing O ring misaligned O ring properly installed O ring in spline grove 1 Install an O Ring in the back groove of each female end of the sled coupling Note The fr...

Page 3: ...a Set Riser or Aluminum Assembled Riser A Pre assembled Certa Set Risers 1 Insert the flanged O ring into the riser The larger ridge faces the riser cap the smaller ridge faces the sled coupling Do not use lubricant Misaligned pipe and sled coupling Properly aligned pipe and sled coupling Push sled coupling onto pipe Push sled coupling onto pipe Insert pointed end of spline first Push spline into ...

Page 4: ...ctured by others 1 The riser consists of the following pieces A riser cap chevron gasket and assembled riser Note NAPCO does not manufacture or warranty risers beyond the riser cap Position riser to align with sled coupling Hand tighten No tools required Hand tighten Place MRDC MR or MDC onto riser first Hand tighten Place sprinkler head onto MRDC MR or MDC hand tighten Place MRDC MR or MDC onto r...

Page 5: ...MRDC MR or MDC onto riser first Notes 1 Splines should be inserted the same direction to facilitate the removal of the splines when the pipe is removed from the field with the automatic pipe removal system Please refer to the Field Layout Planning Guide and the Lateral Field Installation sections 2 All 1 2 riser stubs below the quick disconnect hook must be a minimum of 2 25 in length to ensure fu...

Page 6: ... the O ring in the female end of each sled coupling 3 While the pipe is still on the flatbed trailer verify the male end of the pipe is clean and lubricated 4 Place roller tables in line with intended furrow Note The use of roller tables is preferred but not required Notes 1 Avoid getting lubricant in the spline grooves 2 Do not use excess lubricant Pipe roller table setup Pipe roller table setup ...

Page 7: ...tion as it relates to pipe removal Connecting to tractor hitch 1 Connecting to tractor hitch 2 Final connection Final connection Final connection another option Final connection another option Connecting pipe to tractor Connecting pipe to tractor Insert pipe into sled coupling Insert pipe into sled coupling Insert pipe into sled coupling Correctly inserted splines Insert pointed end of spline firs...

Page 8: ...ect lateral line to the rest of the system See the Field Layout and Main Line Pipe Assembly and Installation sections 10 Flush lateral lines and install the end plugs Flush lateral pipe End plug Install end plug Certa Set pipe entirely installed in an H design pattern Certa Set pipe entirely installed in the field Certa Set pipe entirely installed in a U design pattern Certa Set pipe installed in ...

Page 9: ...led coupling 1 Begin by holding the spline upside down above the top of the coupling with the white stripe facing outward away from the center of the coupling 2 Feed the flared end of the spline into the spline hole ensuring that the end of the spline contacts the coupling in the spline groove on the coupling ID 3 Continue to feed the spline counter clockwise through the spline hole and into the c...

Page 10: ...pect the female end of the coupling or tapped coupling ensuring the O Ring is properly seated in the rear groove and that the spline groove front is clean and free of dirt and debris 2 Lubricate the O ring Notes 1 Avoid getting lubricant in the spline grooves 2 Do not use excess lubricant O ring missing O ring in spline groove O ring properly installed O ring misaligned Lubricant Applying lubrican...

Page 11: ...ipe above the floor of the V ditch is available At minimum a 4 x 4 block in good condition should be used 6 Insert spigot end of pipe into coupling Pipe and coupling must be aligned in order for pipe to seat properly against the O Ring Pipe should slide straight into the coupling without deflection Pipe with debris Lubricate spigot Lubricate spigot Backhoe Tractor tire Misaligned pipe and coupling...

Page 12: ... good condition Never hammer on pipe that does not seat Check alignment then apply pressure with a digging bar again In difficult situations where pipe is properly lubricated and aligned use one digging bar to maintain pressure and a second bar to apply additional pressure In most cases when pipe is properly seated you will feel hear a slight pop If the spline will not easily insert into the hole ...

Page 13: ...tripped if threads are not aligned properly Take precautionary steps to prevent cross threading Best Practices Turn the pipe backward so the female end drops in then tighten This eliminates stripped threads Tapped coupling Threaded adapter Nelson valve Tapped coupling assembly Nelson valve installed onto tapped coupling Secure Nelson valve installed onto tapped coupling with spline Nelson valve ...

Page 14: ...te the transition fitting Tee or elbow should be at 90 degrees so that the outlet is facing up LATERAL PIPE FIELD REMOVAL Certa Set Lateral Pipe Field Removal Guide Swing joints are on both sides of the Nelson valve Nelson valve with burried main line Elbows connecting lateral pipe runs Tees End plug to be removed Remove spline Remove end plug Drain piping 3 Follow all operating procedures and saf...

Page 15: ...n parallel with the head of the field Using a spotter align both ramps of the machine with the pipeline ensuring almost perfect alignment across the machine 7 Place an extra section of pipe in the AIM Machine and CLOSE the drive wheels 8 Connect the pipe in the machine to the first coupling of the pipeline Silt and foliage surrounding sled coupling Connecting to tractor to break pipe free for remo...

Page 16: ...ressure off of the coupling The machine operator will then remove the spline and place it in a bucket 11 Pull the outboard lever to the outboard direction first separating the pipe from the coupling 12 Repeat Steps 8 10 until the entire pipeline is removed Leave the last piece of pipe in the machine to facilitate the connection to the next lateral pipe run to be removed 13 Repeat steps 7 11 until ...

Page 17: ... and drain line completely Failure to drain lines will result in damage to the pipe and will void the warranty 4 Connect the pipeline to the tractor using a pulling connection 5 Slowly pull the pipeline ensuring that it is not binding up on any obstruction 6 Tow pipe into place in next field and reconnect as necessary Swing joints are on both sides of the Nelson valve Nelson valve with buried main...

Page 18: ...1 855 624 7473 napcopipe com NAPCO 2801 Post Oak Blvd Suite 600 Houston TX 77056 2019 NAPCO a Westlake company All rights reserved AG BR 002 US EN 0819 2 ...