background image

05

Cliprail Zone Pack

04

Cliprail Zone Pack

4.0  Installation

3.0  Preparation

Ensure that the surface of the concrete slab onto which the
system is to be laid is both clean and dry and the area 
is cordoned off to prevent unauthorised access.

Underfloor heating pipework is much easier to handle when
warm. If possible store the pipework in a heated room 
for 24 hours prior to installation. Do not install underfloor
heating in temperatures below 0ºC.

Plan the pipe route carefully to ensure each heating loop does
not exceed 120m in length. A basic typical pipe layout 
is shown below. See Figure 1.

The two-port manifold is installed at a convenient location in,
or near the area to be heated. The heating pipework is
connected to the flow manifold (which contains the air vent)
and then laid out in the required configuration. Pipes are held
in place with a clip rail system, which is fixed with self-adhesive
strips to a separation membrane (supplied and laid by others)
placed over the insulation (supplied and laid by others).

The tails of return pipework are then cut to length and
connected to the return manifold (which contains the pressure
gauge). All pipework is fed to the manifold using pre-formed
pipe bend supports to ensure no creasing occurs during
transition from horizontal to vertical alignment. The pipework is
inserted into manifold ports and secured using brass
compression ring manifold connectors. The underfloor heating
layout is designed such as to have no joints other than the
connections at the manifold.

Prior to the screed being laid, the underfloor heating pipework
should be filled with water and tested to a pressure of 3 bar
gauge. The area under full test is to be protected from site
personnel during the test period. This pressure should be
maintained for a minimum of 2 hours and then reduced to a
working pressure of 1 bar gauge in accordance with current
H&S requirements. This should then be held during concreting
to ensure any damage resulting in a leak is identified
immediately. Once concreting is completed, the pressure may
be released.

Following curing of the screed, the underfloor heating system
can be filled with water, turned on and the flow temperatures
slowly elevated in accordance with our recommendations.

Manifold

Single-Zone

Fig. 1

PUMP

LOOP 1 FL

OW

FLOW FROM PRIMARY

HEATING CIRCUIT

RETURN TO PRIMARY

HEATING CIRCUIT

LOOP 1 RETURN

MIXING VALVE

LOOP 2 RETURN

LOOP 2 FL

OW

FLOW MANIFOLD

RETURN MANIFOLD

MANUAL AIR VENT

PRESSURE GAUGE

1. Border Edge Strip

l

MYSON FLOORTEC Border Insulation (Part No. 50220) is 
placed around the perimeter of the room. It may be fixed to 
the walls by nails or clips positioned above the screed level. 
Care must be taken to ensure any damp proof membrane 
in the wall is not perforated. The polythene skirt of the 
Border insulation must be lifted and placed over the floor 
insulation prior to the screed being laid.

2. Insulation

l

It is the responsibility of the builder to ensure the floor 
insulation to which the Cliprail is fitted complies with 
the Building Regulations. The insulation must be securely 
fitted and taped before screeding. The required insulation is 
not supplied by MYSON FLOORTEC.

3. Loop Layouts/Coil Cuts

l

Survey the area to be used and carefully plan the heating 
loop configuration. underfloor heating pipework is supplied 
in 120m and 240m rolls for the 20m

2

and 40m

2

packs, 

respectfully. One pipe loop is generally acceptable for an 
area of up to 20m

2

, and two pipe loops should be used for 

areas between 20m

2

and 40m

2

. If two loops are utilised, it is 

important that both loops lengths are equal.

4. MYSON FLOORTEC Underfloor Heating Compact 

Control Unit

l

This must be attached to the wall with the heating flow and 
return isolating valves facing downwards. The mini-manifolds 

are connected to control unit with the flow manifold 
(containing the air vent) to the pump outlet, and the return 
manifold (containing the pressure gauge) to the appropriate 
return connection. The pipe couplings and pressure gauge 
are supplied with the mini-manifolds. PTFE or a similar 
jointing compound should be used in making all 
connections.

17mm PeX-a Pipe; Coupling Set

Note:

PeX-a pipe cannot be installed when ambient

temperature is below freezing.

l

Attach the end of the pipe coil to the flow or return port of 
the manifold using the coupling set. The coupling set is 
made up of a nut, pipe insert and split olive. The nut is 
slipped over the pipe, the insert is then pushed into the end 
of the pipe and the split olive is used as a compression ring 
for the fitting. Take care not to over tighten. PTFE or a 
similar jointing compound may be used in making the 
fittings. Set the pump speed to 2 for a single loop system 
with a floor area of up to 20m

2

and to 3 for a two loop 

system with a floor area between 20m

2

and 40m

2

.

l

If only one heating loop is used, cap off the second loose
connection with the supplied fitting.

5. PeX-a Pipe; Cliprail

l

Carefully remove protective strip along the underside of 
Cliprail and fit to the insulated floor as required. 
Align Cliprail to securely grip the pipework and facilitate a 
uniform floor coverage.

3.0

4.0

21522 Installation Manual_19755 Cliprail manual  20/01/2011  14:46  Page 5

Reviews: