You will need the following:
– Hole saw 55mm (2
1
/4") or jigsaw
– Saw
– Measuring tape
– Asphalt sealant/adhesives
Required floor space
BioLet 55ai width 55 cm (2
1 1
/2") x lenght
11
0 cm (43") (toilet and room for removing tray)
BioLet 65ai width 65 cm (25
1
/2") x lenght
1
35 cm (53") (toilet and room for removing tray)
Pipe installation
The entire pipe, from ceiling and up through cold areas such as attic, must be insulated. This is to prevent
condensation in the ventilation pipe and to increase natural draught.
lnsulation is essential,
even if the
toilet is used only in summer. Do not use bends more than 45° and no rain cap on top of the ventialtion pipe,
only the included netting.
Temperature
The room in which the toilet is installed must be insulated. When the toilet is in use, room temperature should
be at least
1
8° C (65° F) to ensure proper function.The best thing to do is to install a thermostatically
controlled heating element.
During periods when the toilet is not in use the temperature in
the room can be low or even freezing without any damage to the unit.
Air supply
To ensure adequate air supply, a vent through the outer wall should be installed diameter 100 mm (4").
No bathroom fan in the toilet room to avoid back drought, which can lead to odour in the room.
INSTALLATION
4