11 Commissioning transformer at installation site
Maschinenfabrik Reinhausen GmbH 2015
219
4349315/00 EN
VACUTAP® VR®
Checking pressure monitoring device
ü
Check that the pressure monitoring device is operating properly before
putting the transformer into operation:
1.
Ground the transformer on the high-voltage and low-voltage sides. En-
sure that the working ground connection on the transformer is not re-
moved during testing.
2.
Ensure that transformer remains de-energized during testing.
3.
Deactivate the automatic fire extinguishing device.
4.
Remove the cover cap.
5.
Activate the sensor on the snap-action switch.
ð
Sensor is in the OFF position.
6.
Leave the transformer's danger zone.
7.
Ensure that the transformer's circuit breaker cannot be closed.
ð
Passive protection test
8.
Activate the sensor on the snap-action switch.
ð
Sensor is in the OPERATION position
9.
Leave the transformer's danger zone.
10. Close the transformer's circuit breaker with isolating switches open and
the transformer grounded on all sides.
11. Activate the sensor on the snap-action switch.
ð
Sensor is in the OFF position.
12. Ensure that the transformer's circuit breaker is open.
ð
Active protection test.
13. Activate the sensor on the snap-action switch to reset the pressure
monitoring device.
ð
Sensor is in the OPERATION position
14. Secure the cover cap.
Filling the oil compartment of the on-load tap-changer with
oil
WARNING
Danger of death or severe injury!
Danger of death or severe injury from explosive gases under the on-load
tap-changer head cover, in the pipework system, in the oil conservator or at
the dehydrating breather opening!
► Ensure that there are no naked flames, hot surfaces or sparks (for ex-
ample caused by static charging) in the immediate surroundings and
that none occur.
11.3
11.4
Summary of Contents for VACUTAP VR
Page 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Page 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Page 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Page 266: ......
Page 267: ......