20
Continuous Sampling
6.1 Continuous Test Basic Operation
1. Follow the instructions on page 15 for inputting settings - select Continuous Test
Type.
2. Input Test Interval - input the time in minutes that is required between the end of a
test and the begining of a new test.
3. Input:
−
0 (zero) ISO Cleanliness Target
−
0 (zero) Nas1638/AS4059E-1 Cleanliness Target
−
0 (zero) AS4059E-2 Cleanliness target (displayed as: *A / *B / *C / *D / *E /
*F after pressing OK)
−
0 (zero) ISO Dirty Alarm Target
−
0 (zero) NAS 1638/AS4059E-1 Dirty Alarm Target
−
0 (zero) AS4059E-2 Dirty Alarm Target (displayed as: *A / *B / *C / *D / *E
/ *F after pressing OK)
4. Insert a tick in the "Log all test results’’ box. This will log every test that is carried
out in the continuous test mode, into the memory of the PML². If the box is not
ticked none of the test results will be stored in the memory of the PML².
5. Press OK button to save settings and return to Remote Device dialogue.
6. Press Flush button to open flush valve - flush indicator turns yellow to indicate
valve is open. Leave valve open until at least 200ml has passed to waste. Refer to
page 36 for more information flushing times.
7. Press Stop button to close flush valve.
8. Press Start button. The PML² will now commence the sampling cycle.
9. The completion progress bar indicates the status of the test. Results will be auto-
matically displayed on the Remote Device dialogue after each test.
10. The status is shown as Waiting between the ending of one test and the starting of
the next test.
Summary of Contents for PML2
Page 1: ...PML Analyser UserGuide 200 052 EN www mpfiltri co uk ...
Page 6: ...6 Introduction Figure 1 ...
Page 38: ...38 Warranty ...
Page 62: ...Appendix K 62 Fault Finding ...