Preliminary Operations: Overview
68P64115A21–B
Sept 2003
1X SC 4812T-MC Multicarrier BTS Optimization/ATP
2-3
Initial Installation of Boards/Modules
Follow the procedure in Table 2-1 to verify the initial installation of
boards/modules.
Table 2-1:
Initial Installation of Boards/Modules
Step
Action
1
Refer to the site documentation and install all boards and modules into the appropriate shelves as
required.
Verify they are NOT SEATED at this time.
NOTE
The Switch Card has a configuration switch that must match the site configuration (see Figure 2-1).
2
As the actual site hardware is installed, record the serial number of each module on a “Serial Number
Checklist” in the site logbook.
NOTE
Configuration Switch in Figure 2-1 shown for 3 Sector
Multicarrier BTS. (Switches 1 and 4 control configuration.)
For Multicarrier, switch 1 should be Down; switch 4 depends on
whether the frame supports 3 or 6 sector.
Figure 2-1:
Switch Card
ti-CDMA-WP-00039-v01-ildoc-ftw
Switch Card
1 2 3 4
ON
BTS
MF
3 Sector
6 Sector
J1
J2
J3
J4
J5
SHIELDS
Configuration
Switch
2