SETTING OF COORDINATE SYSTEM E-29
7
SETTING THE WORK COORDINATE SYSTEM USING G54 TO G59
This section describes the procedure to set the work coordinate system using G54 to G59.
Define the correspondence between the workpiece type and the G code (G54 to G59) on the
WORK OFFSET screen.
Simply specify a program such as G54 X___ Z___, and positioning is carried out in the required
work coordinate system.
<Example 1 For multiple workpieces>
<Example 2 For continuous operation of 1st and 2nd processes>
G54
G55
G56
Assumed Z0 point
1st process
2nd process
3rd process
G54
G55
Assumed Z0 point
1st process
2nd process